On Saturday, Oct. 10 and Sunday, Oct. 11, scaffolding will be removed from the rooftop generator stacks on the Mountain zone. There will be minimal noise as this scaffolding is removed.

On Monday, Oct. 12, a truckload of steel for the new Psychiatry and Behavioral Medicine Unit (PBMU) play yard and porch will be delivered to Children’s via to the hospital entrance on NE 45th St. A mobile crane will be on-site to unload the steel into the play yard. This work will occur after 8 a.m. on Monday morning.

In addition, there will be intermittent drilling between the hours of 8 a.m. and 4 p.m. during the week of Monday, Oct. 12. The drilling will take place on the south side exterior of the building, between the River and Mountain zones.

Thank you for your patience as we continue to improve our facilities for our patients. Please call the construction pager at 206-469-5860 if you have any questions or concerns.