As we count down to the opening of Building Hope in April, I’m pleased to share the latest monthly milestones for the building and related projects.
October – Curb extensions along 40th Avenue NE. Grading and paving on north side of Building Hope site. Elevator from inpatient parking lot to Train entrance. Grading and other work on east, south and west sides of site.
October/December – Construction fence removed. Temporary construction fence in place
December – Sand Point Way improvements, including a new traffic signal and a two-way cycle track in front of the hospital with separate paths for bikes and pedestrians
January – Skybridge exterior
February – Building Hope interior
December-February – Final inspections
March – Interior preparation and training
April – MOVE IN!