The rainy season is here and when the sky opens, the parking stalls on Level 6 of the Ocean parking garage puddle up. To spare patient families and other visitors from stepping into standing water, we’re creating a trench drain just south of the garage entrance to carry away runoff.
Work begins Nov. 11 and will take one to two weeks to complete. All work will occur between 8 a.m. and 5 p.m. The garage entrance will remain open throughout the project.
The project involves cutting a 140-foot long channel through the concrete parking surface and covering it with a grate. Cutting and removing the concrete will produce a large amount of noise.
We appreciate your patience while we make this important improvement.