On Saturday, Jan. 19, construction crews will take down the final tower crane on the Building Cure site. Crews will begin staging at 2 a.m. and the mobile crane needed to dismantle the tower crane will arrive at 4:30 a.m. Dismantling will begin at 7:15 a.m. and should be complete by 8 p.m.
On Sunday, Jan. 20, crews will begin work at 8 a.m. to hoist the rooftop chillers into place. This work will finish around 4 p.m.
All work will be done from within the jobsite fence except for intermittent traffic entering and exiting the site.