Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Feb. 4 to Feb. 10, construction crews are scheduled to perform the following activities:

  • Form concrete curbs
  • Demolish, saw cut and remove asphalt
  • Utilities: install water pipes; cut and cap existing stormwater pipes
  • Prepare dirt pads for drill rigs
  • Drill piles
  • Internal activities: plumbing and pipe installation; install firestop systems and seismic restraints; conduct pressure tests and inspections

Construction noise will be generated throughout the week. The noisiest work will be drilling for the piles (scheduled all week) and the asphalt demolition and saw cutting, which is scheduled for Feb. 7.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.