Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 18 to Nov. 24, construction crews are scheduled to perform the following activities:
• Install rebar and pour concrete for walls, footings, slabs, and curbs
• Strip concrete
• Install waterproofing for walls
• Prep work on electricity transformer vault
• Install mechanical, electrical and plumbing
• Excavation
• Backfill excavated areas
• Internal activities: install new pipe, wiring and pneumatic tube system pathways on Forest A, level 1

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.