Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 6 to Jan. 12, construction crews are scheduled to perform the following activities:

  • Erect structural steel
  • Install decking
  • Install waterproofing for roofing
  • Set stairs
  • Install window framing
  • Install rebar and pour concrete for walls, curbs and stairs
  • Build concrete block walls
  • Install garage fire sprinkler system
  • Internal activities: core drilling; install pipes for pneumatic tube system extension

Construction noise will be generated throughout the week. The loudest external activity will be the structural steel erection; the core drilling will be the loudest internal activity. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.