Building Care construction is underway. From now until building opening in spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 13 to Jan. 19, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Install rebar and pour concrete for walls, curbs, slabs, and stairs
  • Install window framing and jams in walls
  • Install waterproofing for roofing
  • Set stairs
  • Build concrete block walls
  • Install garage fire sprinkler system
  • Move in mechanical, electrical and plumbing equipment
  • Installs generator muffler and fuel oil piping
  • Grading
  • Internal activities: install pipes for pneumatic tube system extension

Construction noise will be generated throughout the week. The loudest external activity will be the structural steel erection. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.