Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Feb. 17 to Feb. 23, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Pour concrete for walls, curbs, slabs, stairs and duct bank
  • Install fireproofing
  • Install mechanical, electrical and plumbing equipment
  • Paint concrete
  • Build exterior panels
  • Set stairs
  • Set elevator machines
  • Frame walls and doors
  • Install sprinkler system
  • Build concrete block walls
  • Set air handling units
  • Install rain leaders
  • Install natural gas line (see Feb. 7 Construction Blog post for details)
  • Internal activities in River building: install pipes for pneumatic tube system extension

Notes: The roofing and waterproofing activities will generate odors. The natural gas line work will be done at night within 40th Avenue NE and will restrict some parking on the street (see the Feb. 7 Construction Blog post for details).

Construction noise will be generated throughout the week. The loudest external activities will be the structural steel erection. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.