Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 2 to March 8, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Pour concrete for walls, curbs, slabs, stairs and duct bank
  • Install mechanical, electrical and plumbing equipment
  • Install fireproofing
  • Set and weld walls
  • Set stairs
  • Install mechanical, electrical and plumbing equipment
  • Install mechanical room equipment
  • Build concrete block walls
  • Install glass
  • Install rain leaders
  • Install storm drain and fuel oil pipes
  • Internal activities in River building: install pipes for pneumatic tube system extension

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.