Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 6 to July 12, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Load in and set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Install soil
  • Interior activities: install drywall, insulation, and mechanical, electrical and plumbing for new chapel location on River A level 7; install mechanical, electrical and plumbing in lower level 1 of Forest A for future connections; set up infection prevention barriers and demolish existing ceiling tiles on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.