Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Nov. 30 to Dec. 6, construction crews are scheduled to perform the following activities:
- Framing
- Paint
- Install roofing
- Install windows
- Install ductwork
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Waterproofing
- Install siding
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical, telecommunication, machine and generator rooms
- Install flooring
- Build out interior spaces
- Install sprinkler system
- Building connection work:
- Demolish walls and ceiling and install utility wiring on level 3 of River C
- Paint and install utility wiring and ceiling on level 5 of River C
- Install expansion joint covers, utility wiring, and ceiling on level 6 of River C
- Install expansion joint covers on level 7 of River C
- Paint and install ceiling on level L1 of Forest A
- Paint and install flooring on level 1 of Forest A
- Remove infection prevention barriers on level 2 of Forest A
- Paint, install corner guards, and remove infection prevention barriers on level 3 of Forest A
- Paint and install ceiling, utility wiring, and corner guards on level 4 of Forest A
- Paint and install ceiling and utility wiring on level 5 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.