Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 28 to Jan. 3, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Install drywall
  • Install trim
  • Tape and paint
  • Install metal sheeting and panels
  • Install stone cladding on exterior
  • Install mechanical and electrical wiring and plumbing equipment
  • Install sprinkler system
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical and telecommunication rooms
  • Begin Terrazzo flooring install in main entry
  • Building connection work:
    • Install doors, complete soffits and paint on level 3 of River C
    • Cleaning on levels 4 and 5 of River C
    • Final inspections on level 1 of Forest A stair egress; reopen in advance of FA Staff Entrance Closure

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Jan. 1.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.