Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Feb. 1 to Feb. 7, construction crews are scheduled to perform the following activities:
- Build out interior spaces
- Framing
- Paint
- Install roofing
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Remove scaffolding
- Install drywall
- Install elevator equipment
- Install ceilings
- Saw cut existing curb and demolish hard surfaces in north parking lot
- Install flooring
- Building connection work:
- Install ceiling, utility wiring, and drywall on level 3 of River C
- Paint and Install flooring on level 7 of River C
- Excavation and form footings on level 1 of Forest A
- Install metal panels and trim utility wiring on level 9 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. The loudest external activities will be the saw cutting and demolishing on the north side of the construction site. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.