Archive for May 2021

Upcoming Building Care Construction Activities: June 7 to June 13

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 7 to June 13, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Paint
  • Waterproofing
  • Pressure washing
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install ceilings
  • Install flooring
  • Install storm drains and pipes
  • Demolish temporary duct bank and pad
  • Saw cut asphalt and concrete
  • Excavation and backfilling
  • Grading
  • Install soil
  • Install underground oxygen line
  • Building connection work:
    • Install walls and utility wiring on level 3 of River C
    • Set up infection prevention barriers, demolition, paint, and install signage on level 7 of River C
    • Install glass, install doors, trim utility wiring, and install signage on level 1 of Forest A

Construction noise will be generated throughout the week. The saw cutting and demolishing activities will generate the most noise. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Grading and Landscaping Work near NE 45th St and 40th Ave NE

Grading and landscaping work will begin next week to prepare a site that will serve as a garden respite space for patients and families just south of the Friends of Costco building. Some small trees will be relocated within the garden area during this work, but no trees will be removed. The grading and landscaping work is being done in preparation for a wood garden pavilion that will be assembled onsite later this summer or fall. All materials will be brought in via the adjacent footpaths and materials will be staged in the driveway turn around area just south of the Emergency Department entrance on 40th Ave NE.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday.

Please call 206-987-8000 or email [email protected] with questions.


Hello world!

Welcome to WordPress. This is your first post. Edit or delete it, then start writing!


Upcoming Building Care Construction Activities: May 17 to May 23

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 17 to May 23, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Install glass canopy
  • Paint
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install ceilings
  • Install flooring
  • Install storm drains and pipes
  • Form and pour concrete stairs and walkways
  • Demolish asphalt and concrete
  • Excavation
  • Building connection work:
    • Core drilling and demolish walls, ceilings, and plumbing on level 3 of River C
    • Set up infection prevention barriers, demolish elevator front, and paint on level 7 of River C
    • Install flooring, windows, and siding on level 1 of Forest A

Construction noise will be generated throughout the week. The demolishing of asphalt and concrete will generate the most noise. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Upcoming Building Care Construction Activities: May 10 to May 16

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 10 to May 16, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Install asphalt
  • Install glass at canopy and vestibule
  • Paint
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install ceilings
  • Install flooring
  • Form and pour concrete stairs and walkways
  • Demolish asphalt and concrete
  • Install irrigation
  • Install topsoil
  • Saw cut concrete and asphalt
  • Building connection work:
    • Set up infection prevention barriers and demolish walls, ceilings, and plumbing on level 3 of River C
    • Paint and install flooring, windows, and siding on level 1 of Forest A

Construction noise will be generated throughout the week. The saw cutting and demolishing of asphalt and concrete will generate the most noise. The asphalt installation will generate some odors. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.