There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 24 to May 30, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Install glass at vestibule
  • Paint
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install ceilings
  • Install flooring
  • Install storm drains and pipes
  • Form and pour concrete stairs and walkways
  • Demolish asphalt and concrete
  • Excavation and backfilling
  • Install irrigation
  • Building connection work:
    • Install utility wiring and walls; clean; and remove infection prevention barriers on level 3 of River C
    • Install flooring and siding on level 1 of Forest A

Construction noise will be generated throughout the week. The demolishing of asphalt and concrete will generate the most noise. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.