There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 14 to June 20, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Paint
  • Waterproofing
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install ceilings
  • Install flooring
  • Excavation
  • Pour concrete walkways and stairs
  • Grading
  • Restore rain garden
  • Install soil and mulch
  • Install irrigation
  • Building connection work:
    • Install utility wiring and brackets on level 3 of River C
    • Set up infection prevention barriers and demolition on level 7 of River C
    • Paint and install corner guards on level 1 of Forest A

Construction noise will be generated throughout the week. The mulch installation will generate some odors. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.