Building Care

Category

Upcoming Building Care Construction Activities: Aug. 10 to Aug. 16

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 10 to Aug. 16, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install irrigation
  • Install gravel maintenance path
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, frame doorway, install drain, install ceiling grid, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install ceiling panels, tile, stone, and flooring in new chapel location on River A level 7
    • Install utility wiring, install drywall, and paint in conference rooms on Forest A level 2
  • Building connection work:
    • Install doors, paint, and remove infection prevention barriers on lower level 1 of Forest A
    • Set up infection prevention barriers on level 2 of Forest A
    • Set up infection prevention barriers and begin demolition on level 3 of Forest A
    • Demolition and steel installation on level 4 of Forest A
    • Pour slab edge, set walls, and install seismic joints on level 5 of Forest A
    • Install seismic joints and mechanical, electrical, and plumbing connections on level 6 of Forest A
    • Install seismic joints and mechanical, electrical, and plumbing connections on level 7 of Forest A
    • Install utility wiring and complete framing on level 8 of Forest A
    • Install new roofing, add hot rubber on gurney path, and set up infection prevention barriers on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 3 to Aug. 9

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 3 to Aug. 9, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install glass
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Set air handling units
  • Install fire sprinkler systems
  • Install flooring
  • Install soil
  • Install irrigation
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, frame doorway, install plywood, and paint on River B level 3 in old vending machine location
    • Paint, install ceiling panels, and install tile and stone in new chapel location on River A level 7
    • Set up infection prevention barrier, demolition, rough-in utility wiring, and install drywall in conference rooms on Forest A level 2
  • Building connection work:
    • Install ceiling panels, seal floors, and install utility wiring and pipes on lower level 1 of Forest A
    • Set up infection prevention barriers and begin demolition on level 4 of Forest A
    • Demolition and steel installation on level 5 of Forest A
    • Install steel and walls on level 6 of Forest A
    • Install walls and seismic joints on level 7 of Forest A
    • Install utility wiring, pipes, insulation, drywall and seismic joint covers on level 8 of Forest A
    • Form and pour curbs, frame and install drywall, install new roofing, and set up infection prevention barriers on level 9 of Forest A

Construction noise will be generated throughout the week. The soil installation and fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 27 to Aug. 2

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 27 to Aug. 2, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install glass
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install pneumatic tube system stations
  • Install fire sprinkler systems
  • Install flooring
  • Install soil
  • Build out interior spaces
  • Work in existing buildings: demolish flooring and drywall, saw cut floor, install drain, install utility wiring and pipes, and install drywall on River B level 3 in old vending machine location; paint and install ceiling panels in new chapel location on River A level 7
  • Building connection work: paint, install ceiling panels, and install utility wiring and pipes on lower level 1 of Forest A; set up infection prevention barriers and begin demolition on level 5 of Forest A; demolition and steel installation on level 6 of Forest A; install steel and walls on level 7 of Forest A; install utility wiring and pipes on level 8 of Forest A; frame and install drywall, demolish existing roofing, install new roofing, and set roof drains on level 9 of Forest A

Construction noise will be generated throughout the week. The soil installation will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 20 to July 26

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 20 to July 26, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install pneumatic tube system equipment
  • Install fire sprinkler systems
  • Install flooring
  • Set air handling units
  • Install soil
  • Build out interior spaces
  • Interior activities: set up infection prevention barrier and demolish flooring and drywall on River B level 3 in old vending machine location; paint in new chapel location on River A level 7; set up infection prevention barriers on level 6 of Forest A for future connections; demolition on level 7 of Forest A for future connections; install seismic joints and mechanical, electrical, and plumbing on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. The soil installation will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 13 to July 19

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 13 to July 19, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Power vault buildout by Seattle City Light
  • Interior activities: relocate vending machines to new location on River B level 3; install drywall for new chapel location on River A level 7; install insulation and drywall in lower level 1 of Forest A for future connections; set up infection prevention barrier on level 7 of Forest A for future connections; demolish existing ceiling tiles, rework plumbing and install steel on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 6 to July 12

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 6 to July 12, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Load in and set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Install soil
  • Interior activities: install drywall, insulation, and mechanical, electrical and plumbing for new chapel location on River A level 7; install mechanical, electrical and plumbing in lower level 1 of Forest A for future connections; set up infection prevention barriers and demolish existing ceiling tiles on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 29 to July 5

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 29 to July 5, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Install pneumatic tube system
  • Load in and set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Install soil
  • Interior activities: frame walls and install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The job site will be closed Saturday, July 4, for Independence Day.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 22 to June 28

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 22 to June 28, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Set rooftop chillers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Install pneumatic tube system
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Interior activities: install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 15 to June 21

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 15 to June 21, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Set up lift system
  • Set rooftop chillers
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Interior activities: install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 8 to June 14

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 8 to June 14, construction crews are scheduled to perform the following activities:

  • Erect cladding and support steel
  • Pour concrete for walls, shafts, slabs, pads, curbs and decks
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Set rooftop chillers
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Install exterior sheeting
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Interior activities: paint and clean on River B level 3 for new vending machines location; demolish walls and install mechanical, electrical and plumbing for new chapel location on River A level 7.

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.