Building Care

Category

Upcoming Building Care Construction Activities: Sept. 21 to Sept. 27

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 21 to Sept. 27, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, and landings
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install metal panels
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Electrical power installation (Seattle City Light)
  • Work in existing buildings:
    • Install ice maker, sink, shelves, and IT equipment on River B level 3 for Starbucks coffee cart
    • Install panels, doors, glass, and signage in new chapel location on River A level 7
  • Building connection work:
    • Saw cutting, pour stairs and install steel on level 1 of Forest A
    • Set walls on level 5 of Forest A
    • Set walls and install seismic joints and utility connections on level 6 of Forest A
    • Complete framing and install utility wiring and insulation on level 7 of Forest A
    • Install utility wiring, insulation, drywall, and seismic joint covers on level 8 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 14 to Sept. 20

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 14 to Sept. 20, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install metal panels
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Electrical power installation (Seattle City Light)
  • Work in existing buildings:
    • Paint and install ceiling tiles, grease interceptor, sink, dishwasher and water heater on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install utility wiring, countertops, panels, and doors in new chapel location on River A level 7
  • Building connection work:
    • Saw cutting, set walls, pour stairs and install steel and fireproofing on level 1 of Forest A
    • Complete framing and install seismic joints, utility wiring, and pneumatic tube connections on level 2 of Forest A
    • Complete framing and install utility wiring and pneumatic tube connections on level 3 of Forest A
    • Install utility wiring, insulation, drywall, and seismic joint covers on level 4 of Forest A
    • Install drywall and seismic joint covers on level 5 of Forest A
    • Install seismic joint covers on level 6 of Forest A
    • Install seismic joint covers on level 7 of Forest A
    • Patch ceilings and trim utility wiring on level 8 of Forest A
    • Install flooring on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 7 to Sept. 13

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 7 to Sept. 13, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install metal panels
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Work in existing buildings:
    • Install flooring, run fiber optic cable, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install paneling, panel supports, carpet, and utility wiring in new chapel location on River A level 7
  • Building connection work:
    • Install stairs, install steel beam, and saw cutting on level 1 of Forest A
    • Set walls and install seismic joints on level 2 of Forest A
    • Install seismic joints, utility wiring, and pneumatic tube connections on level 3 of Forest A
    • Install utility wiring, install pneumatic tube connections, and complete framing on level 4 of Forest A
    • Install mechanical, electrical, plumbing, and insulation on level 5 of Forest A
    • Install mechanical, electrical, plumbing, insulation, drywall, and seismic joint covers on level 6 of Forest A
    • Install insulation, drywall, and seismic joint covers on level 7 of Forest A
    • Paint, patch ceilings, and trim utility wiring on level 8 of Forest A
    • Install drywall, paint, and trim utility wiring on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 31 to Sept. 6

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 31 to Sept. 6, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set exterior walls
  • Install metal panels
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring, pipes, ceiling tiles, and flooring on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install paneling and wall coverings in new chapel location on River A level 7
  • Building connection work:
    • Demolition and relocation of mechanical, electrical, and plumbing on level 1 of Forest A
    • Set walls, install seismic joints, and install mechanical, electrical, plumbing, and pneumatic tube connections on level 2 of Forest A
    • Set walls and install seismic joints on level 3 of Forest A
    • Complete framing and install mechanical, electrical, plumbing, and insulation on level 4 of Forest A
    • Install mechanical, electrical, plumbing, insulation, drywall, and seismic joint covers on level 5 of Forest A
    • Install insulation, drywall, and seismic joint covers on level 6 of Forest A
    • Install mechanical, electrical, plumbing, insulation, drywall, and seismic joint covers on level 7 of Forest A
    • Install seismic joint covers on level 8 of Forest A
    • Install metal panels and drywall on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 24 to Aug. 30

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 24 to Aug. 30, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install pneumatic tube stations
  • Core drilling
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, install ceiling grid, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install paneling, doors, and windows in new chapel location on River A level 7
  • Building connection work:
    • Set up infection prevention barriers and begin demolition on level 1 of Forest A
    • Demolition and set walls on level 2 of Forest A
    • Install steel and set walls on level 3 of Forest A
    • Install seismic joints and connections for mechanical, electrical, plumbing, and pneumatic tube system on level 4 of Forest A
    • Complete framing and install connections for mechanical, electrical, plumbing, and pneumatic tube system on level 5 of Forest A
    • Complete framing and install connections for mechanical, electrical, and plumbing on level 6 of Forest A
    • Complete framing and install connections for mechanical, electrical, and plumbing on level 7 of Forest A
    • Install utility wiring, insulation, and drywall on level 8 of Forest A
    • Install utility wiring and waterproofing on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 17 to Aug. 23

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 17 to Aug. 23, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install pneumatic tube stations
  • Core drilling
  • Install insulation
  • Install flooring
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, install ceiling grid, install drywall, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install flooring, paneling, and doors in new chapel location on River A level 7
    • Install utility wiring and paint in conference rooms on Forest A level 2
  • Building connection work:
    • Remove infection prevention barriers on lower level 1 of Forest A
    • Set up infection prevention barriers on level 1 of Forest A
    • Set up infection prevention barriers and begin demolition on level 2 of Forest A
    • Demolition and install steel on level 3 of Forest A
    • Set walls and install seismic joints on level 4 of Forest A
    • Install seismic joints, install utility wiring, install pneumatic tube connections, and framing on level 5 of Forest A
    • Complete framing and install mechanical, electrical, plumbing, and insulation on level 6 of Forest A
    • Install mechanical, electrical, and plumbing connections and complete framing on level 7 of Forest A
    • Install insulation, drywall, and ceiling tiles and rework infection prevention barriers on level 8 of Forest A
    • Install utility wiring and framing on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 10 to Aug. 16

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 10 to Aug. 16, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install irrigation
  • Install gravel maintenance path
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, frame doorway, install drain, install ceiling grid, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install ceiling panels, tile, stone, and flooring in new chapel location on River A level 7
    • Install utility wiring, install drywall, and paint in conference rooms on Forest A level 2
  • Building connection work:
    • Install doors, paint, and remove infection prevention barriers on lower level 1 of Forest A
    • Set up infection prevention barriers on level 2 of Forest A
    • Set up infection prevention barriers and begin demolition on level 3 of Forest A
    • Demolition and steel installation on level 4 of Forest A
    • Pour slab edge, set walls, and install seismic joints on level 5 of Forest A
    • Install seismic joints and mechanical, electrical, and plumbing connections on level 6 of Forest A
    • Install seismic joints and mechanical, electrical, and plumbing connections on level 7 of Forest A
    • Install utility wiring and complete framing on level 8 of Forest A
    • Install new roofing, add hot rubber on gurney path, and set up infection prevention barriers on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 3 to Aug. 9

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 3 to Aug. 9, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install glass
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Set air handling units
  • Install fire sprinkler systems
  • Install flooring
  • Install soil
  • Install irrigation
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, frame doorway, install plywood, and paint on River B level 3 in old vending machine location
    • Paint, install ceiling panels, and install tile and stone in new chapel location on River A level 7
    • Set up infection prevention barrier, demolition, rough-in utility wiring, and install drywall in conference rooms on Forest A level 2
  • Building connection work:
    • Install ceiling panels, seal floors, and install utility wiring and pipes on lower level 1 of Forest A
    • Set up infection prevention barriers and begin demolition on level 4 of Forest A
    • Demolition and steel installation on level 5 of Forest A
    • Install steel and walls on level 6 of Forest A
    • Install walls and seismic joints on level 7 of Forest A
    • Install utility wiring, pipes, insulation, drywall and seismic joint covers on level 8 of Forest A
    • Form and pour curbs, frame and install drywall, install new roofing, and set up infection prevention barriers on level 9 of Forest A

Construction noise will be generated throughout the week. The soil installation and fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 27 to Aug. 2

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 27 to Aug. 2, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install glass
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install pneumatic tube system stations
  • Install fire sprinkler systems
  • Install flooring
  • Install soil
  • Build out interior spaces
  • Work in existing buildings: demolish flooring and drywall, saw cut floor, install drain, install utility wiring and pipes, and install drywall on River B level 3 in old vending machine location; paint and install ceiling panels in new chapel location on River A level 7
  • Building connection work: paint, install ceiling panels, and install utility wiring and pipes on lower level 1 of Forest A; set up infection prevention barriers and begin demolition on level 5 of Forest A; demolition and steel installation on level 6 of Forest A; install steel and walls on level 7 of Forest A; install utility wiring and pipes on level 8 of Forest A; frame and install drywall, demolish existing roofing, install new roofing, and set roof drains on level 9 of Forest A

Construction noise will be generated throughout the week. The soil installation will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 20 to July 26

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 20 to July 26, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install pneumatic tube system equipment
  • Install fire sprinkler systems
  • Install flooring
  • Set air handling units
  • Install soil
  • Build out interior spaces
  • Interior activities: set up infection prevention barrier and demolish flooring and drywall on River B level 3 in old vending machine location; paint in new chapel location on River A level 7; set up infection prevention barriers on level 6 of Forest A for future connections; demolition on level 7 of Forest A for future connections; install seismic joints and mechanical, electrical, and plumbing on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. The soil installation will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.