Building Care

Category

Upcoming Building Care Construction Activities: Nov. 2 to Nov. 8

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 2 to Nov. 8, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Pressure washing
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Install infection prevention barriers and demolish ceiling, walls, and sprinklers on level 3 of River C
    • Demolish windows and utility wiring and install steel, seismic plate, and insulation on level 4 of River C
    • Framing and install drywall, expansion joint, and utility wiring on level 5 of River C
    • Paint and install expansion joint and drywall on level 6 of River C
    • Framing and install fireproofing on level 7 of River C
    • Seal floors and install ceiling on level L1 of Forest A
    • Paint and install utility wiring, seismic joints, and drywall on level 1 of Forest A
    • Paint on level 2 of Forest A
    • Install utility wiring, insulation, drywall, and seismic joint covers on level 3 of Forest A
    • Install seismic joints, utility wiring, and pneumatic tube connections on level 4 of Forest A
    • Trim utility wiring and install ceiling and flooring on level 5 of Forest A
    • Paint and install doors on level 6 of Forest A
    • Paint and remove infection prevention barriers on level 7 of Forest A
    • Paint and remove infection prevention barriers on level 8 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Oct. 26 to Nov. 1

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Oct. 26 to Nov. 1, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs and walls
  • Framing
  • Paint
  • Install waterproofing
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Building connection work:
    • Set up infection prevention barriers and install temporary power on level 2 of River C
    • Set up infection prevention barriers and demolish walls and windows on level 4 of River C
    • Demolish windows, saw cut concrete, install seismic plate, and frame walls on level 5 of River C
    • Install utility wiring, insulation, and drywall on level 6 of River C
    • Install seismic plate on level 7 of River C
    • Paint and install utility wiring on level L1 of Forest A
    • Install utility wiring, seismic joints, and drywall on level 1 of Forest A
    • Install drywall and seismic joint covers on level 2 of Forest A
    • Install seismic joints, utility wiring, and pneumatic tube connections on level 3 of Forest A
    • Set walls and install utility wiring, seismic joints, and pneumatic tube connections on level 4 of Forest A
    • Paint and install utility wiring and flooring on level 5 of Forest A
    • Install utility wiring and flooring on level 6 of Forest A
    • Install flooring on level 7 of Forest A
    • Install flooring on level 8 of Forest A
    • Install flooring and remove barriers on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Building Care Tower Crane to Be Removed

The Building Care tower crane will be dismantled and removed from the hospital grounds the weekend of Saturday, Oct. 24, and Sunday, Oct. 25. Expect increased noise and truck activity to and from the construction site that weekend. A mobile crane will arrive at the site around noon on Friday, Oct. 23, in preparation for the removal.

Sellen Construction has submitted a noise variance request to the City of Seattle, which would allow work to occur outside standard construction hours as follows:

  • Saturday, Oct. 24, from 6 a.m. to 6 p.m.
  • Sunday, Oct. 25, from 6 a.m. to 6 p.m.

We do not anticipate any impacts to street parking or traffic flow.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Oct. 19 to Oct. 25

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Oct. 19 to Oct. 25, construction crews are scheduled to perform the following activities:

  • Dismantle and remove tower crane (see separate blog post called “Building Care Tower Crane to Be Removed” for details)
  • Pour concrete for slabs and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Set air handling units
  • Building connection work:
    • Set up infection prevention barriers and demolish walls, ceilings, and windows on level 5 of River C
    • Install insulation and drywall on level 6 of River C
    • Form and pour concrete slab on level 7 of River C
    • Paint on level L1 of Forest A
    • Frame walls, set walls, and install utility wiring, steel beam, and fireproofing on level 1 of Forest A
    • Complete framing and install utility wiring and pneumatic tube connections on level 2 of Forest A
    • Set walls and install seismic joints and pneumatic tube connections on level 3 of Forest A
    • Set walls on level 4 of Forest A
    • Install seismic joint covers on level 5 of Forest A
    • Paint on level 6 of Forest A
    • Paint, patch ceiling, trim utility wiring, and install flooring on level 7 of Forest A
    • Trim utility wiring and install flooring on level 8 of Forest A
    • Paint, install drywall, and trim utility wiring on level 9 of Forest A

Construction noise will be generated throughout the week. There will be increased truck activity and noise on Oct. 24 and 25 associated with the removal of the tower crane (see separate blog post called “Building Care Tower Crane to Be Removed” for details). In general, expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

The tower crane removal will take place Saturday, Oct. 24, and Sunday, Oct. 25. All other work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Oct. 12 to Oct. 18

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Oct. 12 to Oct. 18, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs and walls
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, machine and generator rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Set air handling units
  • Electrical power installation (Seattle City Light)
  • Building connection work:
    • Set up infection prevention barriers on level 5 of River C
    • Saw cut concrete, install seismic plate, frame walls, and demolish windows, walls, and ceilings on level 6 of River C
    • Set up infection prevention barriers and start demolition on level 7 of River C
    • Install seismic joint covers and drywall on level L1 of Forest A
    • Install drywall and utility wiring on level 1 of Forest A
    • Set walls on level 2 of Forest A
    • Set walls and install seismic joints on level 3 of Forest A
    • Complete framing and install seismic joints, utility wiring, and pneumatic tube connections on level 4 of Forest A
    • Install utility wiring, insulation, and drywall on level 5 of Forest A
    • Install drywall and seismic joint covers on level 6 of Forest A
    • Trim utility wiring on level 8 of Forest A
    • Install gurneyway connection and drywall on level 9 of Forest A

Construction noise will be generated throughout the week. Internally, the loudest activity will be the demolition and saw cutting on River C levels 6 and 7. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Oct. 5 to Oct. 11

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Oct. 5 to Oct. 11, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs and walls
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, and generator rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Set air handling units
  • Electrical power installation (Seattle City Light)
  • Work in existing buildings:
    • Complete installation of Starbucks kiosk on River B level 3
    • Set up infection prevention barriers and demolish windows, walls, and ceilings on River C level 6
    • Complete work on new chapel location on River A level 7
  • Building connection work:
    • Complete framing and install seismic joints, utility wiring, and insulation on level L1 of Forest A
    • Set walls and install utility wiring and fireproofing on level 1 of Forest A
    • Set walls on level 3 of Forest A
    • Set walls and install seismic joints, utility wiring, and pneumatic tube connections on level 4 of Forest A
    • Set walls, install utility wiring and pneumatic tube connections, and complete framing on level 5 of Forest A
    • Complete framing and install utility wiring and insulation on level 6 of Forest A
    • Install drywall, seismic joint covers, and insulation on level 7 of Forest A
    • Paint, patch ceilings, and trim utility wiring on level 8 of Forest A
    • Install gurneyway connection on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Internally, the loudest activity will be the demolition on River C level 6. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 28 to Oct. 4

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 28 to Oct. 4, construction crews are scheduled to perform the following activities:

  • Pour concrete for pads, walls, shafts, and landings
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Electrical power installation (Seattle City Light)
  • Work in existing buildings:
    • Set up Starbucks kiosk on River B level 3
    • Install wall coverings, clean, and remove infection prevention barriers in new chapel location on River A level 7
  • Building connection work:
    • Complete framing and install seismic joints and utility wiring on level L1 of Forest A
    • Frame walls, saw cut wall, and install fireproofing and steel on level 1 of Forest A
    • Set walls on level 4 of Forest A
    • Set walls on level 5 of Forest A
    • Install seismic joints and utility connections on level 6 of Forest A
    • Complete framing and install utility wiring and seismic joints on level 7 of Forest A
    • Install seismic joint covers on level 8 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Internally, the loudest activity will be the saw cutting on level 1 of Forest A. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 21 to Sept. 27

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 21 to Sept. 27, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, and landings
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install metal panels
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Electrical power installation (Seattle City Light)
  • Work in existing buildings:
    • Install ice maker, sink, shelves, and IT equipment on River B level 3 for Starbucks coffee cart
    • Install panels, doors, glass, and signage in new chapel location on River A level 7
  • Building connection work:
    • Saw cutting, pour stairs and install steel on level 1 of Forest A
    • Set walls on level 5 of Forest A
    • Set walls and install seismic joints and utility connections on level 6 of Forest A
    • Complete framing and install utility wiring and insulation on level 7 of Forest A
    • Install utility wiring, insulation, drywall, and seismic joint covers on level 8 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 14 to Sept. 20

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 14 to Sept. 20, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install metal panels
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Electrical power installation (Seattle City Light)
  • Work in existing buildings:
    • Paint and install ceiling tiles, grease interceptor, sink, dishwasher and water heater on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install utility wiring, countertops, panels, and doors in new chapel location on River A level 7
  • Building connection work:
    • Saw cutting, set walls, pour stairs and install steel and fireproofing on level 1 of Forest A
    • Complete framing and install seismic joints, utility wiring, and pneumatic tube connections on level 2 of Forest A
    • Complete framing and install utility wiring and pneumatic tube connections on level 3 of Forest A
    • Install utility wiring, insulation, drywall, and seismic joint covers on level 4 of Forest A
    • Install drywall and seismic joint covers on level 5 of Forest A
    • Install seismic joint covers on level 6 of Forest A
    • Install seismic joint covers on level 7 of Forest A
    • Patch ceilings and trim utility wiring on level 8 of Forest A
    • Install flooring on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 7 to Sept. 13

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 7 to Sept. 13, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install metal panels
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Work in existing buildings:
    • Install flooring, run fiber optic cable, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install paneling, panel supports, carpet, and utility wiring in new chapel location on River A level 7
  • Building connection work:
    • Install stairs, install steel beam, and saw cutting on level 1 of Forest A
    • Set walls and install seismic joints on level 2 of Forest A
    • Install seismic joints, utility wiring, and pneumatic tube connections on level 3 of Forest A
    • Install utility wiring, install pneumatic tube connections, and complete framing on level 4 of Forest A
    • Install mechanical, electrical, plumbing, and insulation on level 5 of Forest A
    • Install mechanical, electrical, plumbing, insulation, drywall, and seismic joint covers on level 6 of Forest A
    • Install insulation, drywall, and seismic joint covers on level 7 of Forest A
    • Paint, patch ceilings, and trim utility wiring on level 8 of Forest A
    • Install drywall, paint, and trim utility wiring on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.