Building Care

Category

Upcoming Building Care Construction Activities: Jan. 25 to Jan. 31

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 25 to Jan. 31, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Install irrigation system
  • Install gravel maintenance path
  • Install flooring
  • Building connection work:
    • Paint and install ceiling, utility wiring, insulation, and drywall on level 3 of River C
    • Install flooring on level 7 of River C
    • Demolish concrete walkway and excavate for footings on level 1 of Forest A
    • Install expansion joint covers and metal panels on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Jan. 18 to Jan. 24

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 18 to Jan. 24, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Install soil and irrigation system
  • Install flooring
  • Building connection work:
    • Install flooring, trim utility wiring, install doors, and reposition infection prevention barriers on level 3 of River C
    • Remove infection prevention barriers on level 4 of River C
    • Remove infection prevention barriers on level 5 of River C
    • Demolish temporary staff entry vestibule and walls on level 1 of Forest A
    • Install expansion joint covers on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Jan. 11 to Jan. 17

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 11 to Jan. 17, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Building connection work:
    • Framing and install utility writing, sprinklers, ceiling, flooring, and drywall on level 3 of River C
    • Remove infection prevention barriers on level 6 of River C
    • Install infection prevention barriers and demolish temporary staff entry vestibule on level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Jan. 4 to Jan. 10

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 4 to Jan. 10, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Building connection work:
    • Install utility wiring, insulation, drywall, flooring, and ceiling on level 3 of River C
    • Install metal panels and trim utility wiring on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Dec. 28 to Jan. 3

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 28 to Jan. 3, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Install drywall
  • Install trim
  • Tape and paint
  • Install metal sheeting and panels
  • Install stone cladding on exterior
  • Install mechanical and electrical wiring and plumbing equipment
  • Install sprinkler system
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical and telecommunication rooms
  • Begin Terrazzo flooring install in main entry
  • Building connection work:
    • Install doors, complete soffits and paint on level 3 of River C
    • Cleaning on levels 4 and 5 of River C
    • Final inspections on level 1 of Forest A stair egress; reopen in advance of FA Staff Entrance Closure

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Jan. 1.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Dec. 21 to Dec. 27

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 21 to Dec. 27, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Demolish temporary electrical switchboard
  • Building connection work:
    • Framing and install utility wiring, drywall, and sprinklers on level 3 of River C
    • Paint and relocate infection prevention barriers on level 4 of River C
    • Install signage and relocate infection prevention barriers on level 5 of River C
    • Cleaning on level 6 of River C
    • Install expansion joint cover plates on level 7 of River C
    • Paint, trim utility wiring, and patch flooring on level 1 of Forest A
    • Paint and remove infection prevention barriers on level 3 of Forest A
    • Install expansion joint covers and flooring, and remove infection prevention barriers on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Dec. 25.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Dec. 14 to Dec. 20

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 14 to Dec. 20, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Remove temporary power poles and demolish temporary duct bank and switchboard pad
  • Building connection work:
    • Framing and install utility wiring on level 3 of River C
    • Install utility wiring and flooring on level 4 of River C
    • Paint and install flooring on level 5 of River C
    • Paint on level 6 of River C
    • Framing and install expansion joint, utility wiring, drywall, and insulation on level 7 of River C
    • Remove infection prevention barriers on level L1 of Forest A
    • Paint, install flooring, and trim utility wiring on level 1 of Forest A
    • Paint, install ceiling, and trim utility wiring on level 3 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Dec. 7 to Dec. 13

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 7 to Dec. 13, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Waterproofing
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Install utility wiring on level 3 of River C
    • Paint on level 4 of River C
    • Install utility wiring, expansion joint cover plates, and ceiling on level 5 of River C
    • Install flooring on level 6 of River C
    • Paint and remove infection prevention barriers on level L1 of Forest A
    • Paint, install flooring, and trim utility wiring on level 1 of Forest A
    • Remove infection prevention barriers on level 4 of Forest A
    • Paint and install corner guards on level 5 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Nov. 30 to Dec. 6

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 30 to Dec. 6, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Waterproofing
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Demolish walls and ceiling and install utility wiring on level 3 of River C
    • Paint and install utility wiring and ceiling on level 5 of River C
    • Install expansion joint covers, utility wiring, and ceiling on level 6 of River C
    • Install expansion joint covers on level 7 of River C
    • Paint and install ceiling on level L1 of Forest A
    • Paint and install flooring on level 1 of Forest A
    • Remove infection prevention barriers on level 2 of Forest A
    • Paint, install corner guards, and remove infection prevention barriers on level 3 of Forest A
    • Paint and install ceiling, utility wiring, and corner guards on level 4 of Forest A
    • Paint and install ceiling and utility wiring on level 5 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Nov. 23 to Nov. 29

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 23 to Nov. 29, construction crews are scheduled to perform the following activities:

  • Pour concrete for shafts and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Demolish walls and ceilings and install support steel on level 3 of River C
    • Paint and install utility wiring and ceiling on level 6 of River C
    • Install door, insulation, and drywall on level 7 of River C
    • Paint and remove infection prevention barriers on level L1 of Forest A
    • Paint and install flooring on level 1 of Forest A
    • Install corner guards and remove infection prevention barriers on level 2 of Forest A
    • Paint, trim utility wiring, and install ceiling and doors on level 3 of Forest A
    • Paint on level 4 of Forest A
    • Paint on level 5 of Forest A
    • Trim utility wiring on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Nov. 26 and 27 for the Thanksgiving holiday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.