Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 25 to Jan. 31, construction crews are scheduled to perform the following activities:
- Build out interior spaces
- Framing
- Paint
- Install roofing
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Install elevator equipment
- Install ceilings
- Install irrigation system
- Install gravel maintenance path
- Install flooring
- Building connection work:
- Paint and install ceiling, utility wiring, insulation, and drywall on level 3 of River C
- Install flooring on level 7 of River C
- Demolish concrete walkway and excavate for footings on level 1 of Forest A
- Install expansion joint covers and metal panels on level 9 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 18 to Jan. 24, construction crews are scheduled to perform the following activities:
- Build out interior spaces
- Framing
- Paint
- Install roofing
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Install elevator equipment
- Install ceilings
- Install soil and irrigation system
- Install flooring
- Building connection work:
- Install flooring, trim utility wiring, install doors, and reposition infection prevention barriers on level 3 of River C
- Remove infection prevention barriers on level 4 of River C
- Remove infection prevention barriers on level 5 of River C
- Demolish temporary staff entry vestibule and walls on level 1 of Forest A
- Install expansion joint covers on level 9 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 11 to Jan. 17, construction crews are scheduled to perform the following activities:
- Build out interior spaces
- Framing
- Paint
- Install roofing
- Install windows
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical, and telecommunication rooms
- Install flooring
- Building connection work:
- Framing and install utility writing, sprinklers, ceiling, flooring, and drywall on level 3 of River C
- Remove infection prevention barriers on level 6 of River C
- Install infection prevention barriers and demolish temporary staff entry vestibule on level 1 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 4 to Jan. 10, construction crews are scheduled to perform the following activities:
- Build out interior spaces
- Framing
- Paint
- Install roofing
- Install windows
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical, and telecommunication rooms
- Install flooring
- Building connection work:
- Install utility wiring, insulation, drywall, flooring, and ceiling on level 3 of River C
- Install metal panels and trim utility wiring on level 9 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 28 to Jan. 3, construction crews are scheduled to perform the following activities:
- Build out interior spaces
- Framing
- Install drywall
- Install trim
- Tape and paint
- Install metal sheeting and panels
- Install stone cladding on exterior
- Install mechanical and electrical wiring and plumbing equipment
- Install sprinkler system
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical and telecommunication rooms
- Begin Terrazzo flooring install in main entry
- Building connection work:
- Install doors, complete soffits and paint on level 3 of River C
- Cleaning on levels 4 and 5 of River C
- Final inspections on level 1 of Forest A stair egress; reopen in advance of FA Staff Entrance Closure
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Jan. 1.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 21 to Dec. 27, construction crews are scheduled to perform the following activities:
- Framing
- Paint
- Install roofing
- Install windows
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical, and telecommunication rooms
- Install flooring
- Build out interior spaces
- Install sprinkler system
- Demolish temporary electrical switchboard
- Building connection work:
- Framing and install utility wiring, drywall, and sprinklers on level 3 of River C
- Paint and relocate infection prevention barriers on level 4 of River C
- Install signage and relocate infection prevention barriers on level 5 of River C
- Cleaning on level 6 of River C
- Install expansion joint cover plates on level 7 of River C
- Paint, trim utility wiring, and patch flooring on level 1 of Forest A
- Paint and remove infection prevention barriers on level 3 of Forest A
- Install expansion joint covers and flooring, and remove infection prevention barriers on level 9 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Dec. 25.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 14 to Dec. 20, construction crews are scheduled to perform the following activities:
- Framing
- Paint
- Install roofing
- Install windows
- Install ductwork
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical, and telecommunication rooms
- Install flooring
- Build out interior spaces
- Install sprinkler system
- Remove temporary power poles and demolish temporary duct bank and switchboard pad
- Building connection work:
- Framing and install utility wiring on level 3 of River C
- Install utility wiring and flooring on level 4 of River C
- Paint and install flooring on level 5 of River C
- Paint on level 6 of River C
- Framing and install expansion joint, utility wiring, drywall, and insulation on level 7 of River C
- Remove infection prevention barriers on level L1 of Forest A
- Paint, install flooring, and trim utility wiring on level 1 of Forest A
- Paint, install ceiling, and trim utility wiring on level 3 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 7 to Dec. 13, construction crews are scheduled to perform the following activities:
- Framing
- Paint
- Install roofing
- Install windows
- Install ductwork
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Waterproofing
- Install siding
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical, telecommunication, machine and generator rooms
- Install flooring
- Build out interior spaces
- Install sprinkler system
- Building connection work:
- Install utility wiring on level 3 of River C
- Paint on level 4 of River C
- Install utility wiring, expansion joint cover plates, and ceiling on level 5 of River C
- Install flooring on level 6 of River C
- Paint and remove infection prevention barriers on level L1 of Forest A
- Paint, install flooring, and trim utility wiring on level 1 of Forest A
- Remove infection prevention barriers on level 4 of Forest A
- Paint and install corner guards on level 5 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Nov. 30 to Dec. 6, construction crews are scheduled to perform the following activities:
- Framing
- Paint
- Install roofing
- Install windows
- Install ductwork
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Waterproofing
- Install siding
- Install elevator equipment
- Install ceilings
- Build out electrical, mechanical, telecommunication, machine and generator rooms
- Install flooring
- Build out interior spaces
- Install sprinkler system
- Building connection work:
- Demolish walls and ceiling and install utility wiring on level 3 of River C
- Paint and install utility wiring and ceiling on level 5 of River C
- Install expansion joint covers, utility wiring, and ceiling on level 6 of River C
- Install expansion joint covers on level 7 of River C
- Paint and install ceiling on level L1 of Forest A
- Paint and install flooring on level 1 of Forest A
- Remove infection prevention barriers on level 2 of Forest A
- Paint, install corner guards, and remove infection prevention barriers on level 3 of Forest A
- Paint and install ceiling, utility wiring, and corner guards on level 4 of Forest A
- Paint and install ceiling and utility wiring on level 5 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Nov. 23 to Nov. 29, construction crews are scheduled to perform the following activities:
- Pour concrete for shafts and walls
- Framing
- Paint
- Install roofing
- Install windows
- Install ductwork
- Install metal sheeting and panels
- Install mechanical and electrical wiring and plumbing equipment
- Install drywall
- Install siding
- Install ceilings
- Build out electrical, mechanical, telecommunication, machine and generator rooms
- Install flooring
- Build out interior spaces
- Install sprinkler system
- Building connection work:
- Demolish walls and ceilings and install support steel on level 3 of River C
- Paint and install utility wiring and ceiling on level 6 of River C
- Install door, insulation, and drywall on level 7 of River C
- Paint and remove infection prevention barriers on level L1 of Forest A
- Paint and install flooring on level 1 of Forest A
- Install corner guards and remove infection prevention barriers on level 2 of Forest A
- Paint, trim utility wiring, and install ceiling and doors on level 3 of Forest A
- Paint on level 4 of Forest A
- Paint on level 5 of Forest A
- Trim utility wiring on level 9 of Forest A
Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Nov. 26 and 27 for the Thanksgiving holiday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.