Building Care

Category

Upcoming Building Care Construction Activities: April 29 to May 5

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 29 to May 5, construction crews are scheduled to perform the following activities:

  • Excavation
  • Install brackets and scaffold on south wall
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Install rebar for footings
  • Internal activities on L1 of Forest A (Friends of Costco Building): temporary oxygen system shutdowns and new line tie-ins; remove existing oxygen line; install seismic restraints; install new pipe pathways; frame and paint soffit; remove scaffolding and infection prevention barrier
  • Activities south of Forest A: excavation and core drilling

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors (scheduled for April 29 to May 1) and the core drilling (scheduled for May 1 to May 6). The noisiest internal work will be the installation of new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Drill Rig Delivery April 25 at 5 a.m.

A new drill rig will be delivered to the Building Care construction site and unloaded on Thursday, April 25 beginning at 5 a.m. The truck delivering the drill rig will enter and exit the site via the Sand Point Way construction entrance. This work is occurring early to minimize traffic impacts from the oversize load. Moderate noise will be generated during the unloading, but impacts to neighbors should be minimal because the unloading will take place within the fenced construction site. If you have questions, please call 206-987-8000 or email construction@seattlechildrens.org.


Upcoming Building Care Construction Activities: April 22 to April 28

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 22 to April 28, construction crews are scheduled to perform the following activities:

  • Drill piles
  • Install rebar; form and pour concrete footings and slabs
  • Install scaffold brackets on south wall
  • Excavation
  • Internal activities on L1 of Forest A (Friends of Costco Building): install pipes and firestops; install new pipe pathways; install soffit
  • Activities south of Forest A: install site fencing; remove existing landscaping; excavation

Construction noise will be generated throughout the week. The noisiest external work will be the pile-drilling, which is scheduled for April 22 and April 23. The noisiest internal work will be the installation of new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: April 15 to April 21

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 15 to April 21, construction crews are scheduled to perform the following activities:

  • Drill piles
  • Concrete footings: drill and install rebar; form footings
  • Install tie backs/anchors for retaining walls
  • Install “lagging” to prevent cave-ins during earthwork
  • Excavation
  • Pour concrete slab
  • Internal activities on L1 of Forest A (Friends of Costco Building): install pipes and firestops; install new pipe pathways; remove infection prevention barriers

Construction noise will be generated throughout the week. The noisiest external work will be drilling for piles and rebar, which will take place all week. The noisiest internal work will be the installation of new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: April 8 to April 14

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 8 to April 14, construction crews are scheduled to perform the following activities:

  • Drill new piles
  • Demolish some existing piles
  • Excavation
  • Install tie backs/anchors for retaining walls
  • Back fill certain excavated areas
  • Install rebar and stair embeds
  • Internal activities on L1 of Forest A (Friends of Costco Building): install hangers and pipes for multiple systems; install new infection prevention barriers; install new pipe pathways; install firestops

Construction noise will be generated throughout the week. The noisiest external work will be drilling new piles and demolishing some existing piles, which will take place all week. The noisiest internal work will be the installation of new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Wood-Chipping March 26 at Hospital

Wood-chipping will occur at the hospital campus on Tuesday, March 26 within the Building Care construction area. The chipping will generate normal levels of construction noise all day.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: April 1 to April 7

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 1 to April 7, construction crews are scheduled to perform the following activities:

  • Load out current crane from site and load in new crane
  • Excavation
  • Install tie backs/anchors for retaining walls
  • Form concrete slab on grade and wall
  • Internal activities on L1 of Forest A (Friends of Costco Building): core drilling; install pipes, seismic restraints, firestops and hangers for multiple systems; install new pipe pathways; remove infection prevention barrier

The work to load out the current crane and load in the new crane will begin at 5 a.m. on Friday, April 5. The loading and unloading will take place within an existing no parking zone on 40th Avenue NE between NE 45th Street and Sand Point Way NE. This work is occurring early to minimize traffic impacts from the oversize load.

Construction noise will be generated throughout the week. The noisiest external work will be the crane load-out and load-in the morning of April 5 and installing tie backs/anchors, which will take place all week. The noisiest internal work will be the core drilling and installing new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work (other than the crane load-out and load-in discussed above) will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 25 to March 31

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 25 to March 31, construction crews are scheduled to perform the following activities:

  • Excavation
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Form and pour concrete wall
  • Internal activities on L1 of Forest A (Friends of Costco Building): install hangers, pipes, firestops and seismic restraints for multiple systems; replace ceiling grid and tiles; install infection prevention barriers; install new pipe pathways

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors, which will take place all week. The noisiest internal work will be associated with installing new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 18 to March 24

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 18 to March 24, construction crews are scheduled to perform the following activities:

  • Excavation
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Form and pour concrete footing and wall
  • Internal activities on L1 of Forest A: install hangers, pipes, firestops and seismic restraints for multiple water and air systems; core drilling in Forest stairwell #1; install infection prevention barriers; pour equipment pads

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors, which will take place all week. The noisiest internal work will be the core drilling.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 11 to March 17

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 11 to March 17, construction crews are scheduled to perform the following activities:

  • Excavation
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Pour and strip concrete retaining wall
  • Internal activities in Forest A: fire pump replacement work; demolition; install new fire sprinkler valves; saw cutting for reroute of ducts; demolish existing ducts; welding; install infection prevention barriers; core drilling; reframe walls in stairwell 1; install firestops; install new electrical pathways; pour equipment pads

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors, which will take place all week. The noisiest internal work will be the core drilling and demolition.

Expect heavy truck traffic all week as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.