Building Care

Category

Upcoming Building Care Construction Activities: Oct. 25 to Oct. 31

This will be the last weekly update about upcoming Building Care construction activities. Work will continue within the building until spring 2022. We will continue to post to this blog whenever an activity will affect neighbors.

From Oct. 25 to Oct. 31, construction crews will continue building out interior spaces. Wood siding will be installed on the exterior of level 1 of Forest A (Friends of Costco Building) near the staff entrance when the carpenters strike is resolved.

Construction noise will be generated throughout the week. External construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Oct. 11 to Oct. 24

Major construction on Building Care will conclude in October, but work will continue within the building until spring 2022. After October, we will no longer publish weekly posts on the Construction Blog for Building Care. However, we will continue to post to this blog whenever an activity will affect neighbors.

From Oct. 11 to Oct. 24, construction crews are scheduled to perform the following activities:

  • Build out interior spaces on all levels
  • River Entrance vestibule renovations begin (pending carpenter availability); alternative entry into River 3 will be provided adjacent to the vestibule

Construction noise will be generated throughout the week. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Oct. 4 to Oct. 10

Major construction on Building Care will conclude in October, but work will continue within the building until spring 2022. After October, we will no longer publish weekly posts on the Construction Blog for Building Care. However, we will continue to post to this blog whenever an activity will affect neighbors.

From Oct. 4 to Oct. 10, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Painting and striping

Construction noise will be generated throughout the week. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 27 to Oct. 3

Major construction on Building Care will conclude in October, but work will continue within the building until spring 2022. After October, we will no longer publish weekly posts on the Construction Blog for Building Care. However, we will continue to post to this blog whenever an activity will affect neighbors.

From Sept. 27 to Oct. 3, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Painting and striping
  • Install soil and mulch
  • Plant landscaping

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 20 to Sept. 26

Major construction on Building Care will conclude in October, but work will continue within the building until spring 2022. After October, we will no longer publish weekly posts on the Construction Blog for Building Care. However, we will continue to post to this blog whenever an activity will affect neighbors.

From Sept. 20 to Sept. 26, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Remove temporary vestibule at River entrance
  • Restore sidewalks on Sand Point Way NE and 40th Avenue NE (see separate post from Sept. 1 for more information)
  • Install soil and mulch
  • Plant landscaping

Construction noise will be generated throughout the week. Expect heavy truck traffic. The sidewalk restoration is expected to be the loudest external activity. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 13 to Sept. 19

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 13 to Sept. 19, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Restore sidewalks on Sand Point Way NE and 40th Avenue NE (see separate post from Sept. 1 for more information)
  • Install soil and mulch
  • Plant landscaping
  • Install irrigation

Construction noise will be generated throughout the week. Expect heavy truck traffic. The sidewalk restoration is expected to be the loudest external activity. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Sept. 6 to Sept. 12

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 6 to Sept. 12, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Paint
  • Install soil and mulch
  • Plant landscaping
  • Grind and patch asphalt
  • Remove asphalt and prep for new asphalt
  • Pour concrete for curbs
  • Install site furnishings

Construction noise will be generated throughout the week. Expect heavy truck traffic. The asphalt grinding and removal is expected to be the loudest external activity. The asphalt patching may generate some odors. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 30 to Sept. 5

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 30 to Sept. 5, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Install soil and mulch
  • Plant landscaping
  • Saw cut and remove asphalt
  • Install signs
  • Install site furnishings
  • Building connection work:
    • Clean and remove infection prevention barriers on level 3 of River C

Construction noise will be generated throughout the week. Expect heavy truck traffic. The saw cutting is expected to be the loudest external activity. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Aug. 23 to Aug. 29

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 23 to Aug. 29, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Install soil and mulch
  • Plant landscaping
  • Install irrigation system
  • Install signs
  • Install site furnishings and mechanical, electrical and plumbing connections to furniture
  • Install traffic coating at garage ramp
  • Sprinkler dry system testing and alarm device testing
  • Building connection work:
    • Final paint, install signage and rubber base in River 3 lobby

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Building Care Boiler Work to Produce Steam and Noise, Aug. 16 to Aug. 20

From Monday, Aug. 16, to Friday, Aug. 20, construction crews will start up and calibrate the boilers in Building Care at the hospital campus. At times throughout the week, this will generate a “pinging” noise that may be audible to neighbors, and steam will be released from the northwest corner of the building. These periods of noise and steam discharge may last up to four hours at a time between 8 a.m. and 4 p.m.

There is no need for concern if you hear the noise or see the steam. We have notified the fire department of this work. Please call 206-987-8000 or email construction@seattlechildrens.org with questions.