Building Care

Category

Upcoming Building Care Construction Activities: July 13 to July 19

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 13 to July 19, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Power vault buildout by Seattle City Light
  • Interior activities: relocate vending machines to new location on River B level 3; install drywall for new chapel location on River A level 7; install insulation and drywall in lower level 1 of Forest A for future connections; set up infection prevention barrier on level 7 of Forest A for future connections; demolish existing ceiling tiles, rework plumbing and install steel on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 6 to July 12

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 6 to July 12, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Load in and set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Install soil
  • Interior activities: install drywall, insulation, and mechanical, electrical and plumbing for new chapel location on River A level 7; install mechanical, electrical and plumbing in lower level 1 of Forest A for future connections; set up infection prevention barriers and demolish existing ceiling tiles on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 29 to July 5

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 29 to July 5, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Install pneumatic tube system
  • Load in and set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Install soil
  • Interior activities: frame walls and install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The job site will be closed Saturday, July 4, for Independence Day.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 22 to June 28

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 22 to June 28, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Set rooftop chillers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Install pneumatic tube system
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Interior activities: install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 15 to June 21

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 15 to June 21, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Set up lift system
  • Set rooftop chillers
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Interior activities: install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 8 to June 14

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 8 to June 14, construction crews are scheduled to perform the following activities:

  • Erect cladding and support steel
  • Pour concrete for walls, shafts, slabs, pads, curbs and decks
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Set rooftop chillers
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Install exterior sheeting
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Interior activities: paint and clean on River B level 3 for new vending machines location; demolish walls and install mechanical, electrical and plumbing for new chapel location on River A level 7.

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 1 to June 7

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 1 to June 7, construction crews are scheduled to perform the following activities:

  • Erect cladding and support steel
  • Pour concrete for walls, shafts, slabs, pads, curbs and decks
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install temporary roofing
  • Install mechanical and electrical roofing supports
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Set air handling units and supports
  • Interior activities: install mechanical, electrical, plumbing and drywall on River B level 3 for new vending machines location; set up infection prevention barriers and demolish ceiling for new chapel location on River A level 7.

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: May 25 to May 31

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 25 to May 31, construction crews are scheduled to perform the following activities:

  • Erect cladding and support steel
  • Pour concrete for walls, shafts, slabs, pads, curbs, stairs and decks
  • Install fireproofing
  • Paint
  • Install anchors for windows
  • Set and weld exterior walls
  • Install temporary roofing
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Set air handling units and supports
  • Interior activities: install infection prevention barriers, demolish sheetrock, and install mechanical, electrical, and plumbing in River B level 3 at vending machines

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: May 18 to May 24

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 18 to May 24, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Pour concrete for walls, shafts, slabs, pads, curbs and decks
  • Install fireproofing
  • Paint
  • Install anchors for windows
  • Set and weld exterior walls
  • Set up lift system
  • Install temporary roofing
  • Install glass
  • Build elevator care frames
  • Install elevator machines
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install drywall
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Set air handling units
  • Saw cutting for connection points to Forest A
  • Interior activities: repair flooring, paint, clean and remove infection prevention barriers in River B patient family lounge

Construction noise will be generated throughout the week. The saw cutting will be the loudest activity. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: May 11 to May 17

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 11 to May 17, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Pour concrete for walls, shafts, slabs, curbs, decks and stairs
  • Install fireproofing
  • Paint
  • Base construction for connection to River
  • Install anchors for windows
  • Set and weld exterior walls
  • Set up lift system
  • Install glass
  • Build elevator care frames
  • Install gas line
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install drywall
  • Install fire sprinkler systems
  • Install flooring
  • Install plumbing and medical gas risers
  • Demolition and saw cutting for connection points to Forest A
  • Interior activities: install drywall and countertops in River B patient family lounge

Construction noise will be generated throughout the week. The demolition and saw cutting activities will be the loudest. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.