Building Care

Category

Upcoming Building Care Construction Activities: Jan. 18 to Jan. 24

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 18 to Jan. 24, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Install soil and irrigation system
  • Install flooring
  • Building connection work:
    • Install flooring, trim utility wiring, install doors, and reposition infection prevention barriers on level 3 of River C
    • Remove infection prevention barriers on level 4 of River C
    • Remove infection prevention barriers on level 5 of River C
    • Demolish temporary staff entry vestibule and walls on level 1 of Forest A
    • Install expansion joint covers on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Upcoming Building Care Construction Activities: Jan. 11 to Jan. 17

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 11 to Jan. 17, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Building connection work:
    • Framing and install utility writing, sprinklers, ceiling, flooring, and drywall on level 3 of River C
    • Remove infection prevention barriers on level 6 of River C
    • Install infection prevention barriers and demolish temporary staff entry vestibule on level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Upcoming Building Care Construction Activities: Dec. 21 to Dec. 27

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 21 to Dec. 27, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Demolish temporary electrical switchboard
  • Building connection work:
    • Framing and install utility wiring, drywall, and sprinklers on level 3 of River C
    • Paint and relocate infection prevention barriers on level 4 of River C
    • Install signage and relocate infection prevention barriers on level 5 of River C
    • Cleaning on level 6 of River C
    • Install expansion joint cover plates on level 7 of River C
    • Paint, trim utility wiring, and patch flooring on level 1 of Forest A
    • Paint and remove infection prevention barriers on level 3 of Forest A
    • Install expansion joint covers and flooring, and remove infection prevention barriers on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Dec. 25.

Please call 206-987-8000 or email [email protected] with questions.


Upcoming Building Care Construction Activities: Nov. 9 to Nov. 15

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 9 to Nov. 15, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs, shafts and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Install infection prevention barriers and demolish ceiling and walls on level 3 of River C
    • Framing and install drywall and utility wiring on level 4 of River C
    • Install expansion joint, utility wiring, and insulation on level 5 of River C
    • Paint and install ceiling, utility wiring, drywall, and expansion joint on level 6 of River C
    • Framing and install utility wiring on level 7 of River C
    • Seal floors and install ceiling on level L1 of Forest A
    • Framing and install utility wiring, drywall, and pneumatic tube connections on level 1 of Forest A
    • Install ceilings, utility wiring, and flooring on level 2 of Forest A
    • Install flooring and seismic joint covers on level 3 of Forest A
    • Install flooring, utility wiring, insulation, drywall, and seismic joint covers on level 4 of Forest A
    • Install flooring and seismic joints on level 5 of Forest A
    • Install corner guards and remove infection prevention barriers on level 6 of Forest A
    • Remove infection prevention barriers on level 7 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Upcoming Building Care Construction Activities: Oct. 12 to Oct. 18

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Oct. 12 to Oct. 18, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs and walls
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, machine and generator rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Set air handling units
  • Electrical power installation (Seattle City Light)
  • Building connection work:
    • Set up infection prevention barriers on level 5 of River C
    • Saw cut concrete, install seismic plate, frame walls, and demolish windows, walls, and ceilings on level 6 of River C
    • Set up infection prevention barriers and start demolition on level 7 of River C
    • Install seismic joint covers and drywall on level L1 of Forest A
    • Install drywall and utility wiring on level 1 of Forest A
    • Set walls on level 2 of Forest A
    • Set walls and install seismic joints on level 3 of Forest A
    • Complete framing and install seismic joints, utility wiring, and pneumatic tube connections on level 4 of Forest A
    • Install utility wiring, insulation, and drywall on level 5 of Forest A
    • Install drywall and seismic joint covers on level 6 of Forest A
    • Trim utility wiring on level 8 of Forest A
    • Install gurneyway connection and drywall on level 9 of Forest A

Construction noise will be generated throughout the week. Internally, the loudest activity will be the demolition and saw cutting on River C levels 6 and 7. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Upcoming Building Care Construction Activities: Aug. 17 to Aug. 23

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 17 to Aug. 23, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install pneumatic tube stations
  • Core drilling
  • Install insulation
  • Install flooring
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, install ceiling grid, install drywall, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install flooring, paneling, and doors in new chapel location on River A level 7
    • Install utility wiring and paint in conference rooms on Forest A level 2
  • Building connection work:
    • Remove infection prevention barriers on lower level 1 of Forest A
    • Set up infection prevention barriers on level 1 of Forest A
    • Set up infection prevention barriers and begin demolition on level 2 of Forest A
    • Demolition and install steel on level 3 of Forest A
    • Set walls and install seismic joints on level 4 of Forest A
    • Install seismic joints, install utility wiring, install pneumatic tube connections, and framing on level 5 of Forest A
    • Complete framing and install mechanical, electrical, plumbing, and insulation on level 6 of Forest A
    • Install mechanical, electrical, and plumbing connections and complete framing on level 7 of Forest A
    • Install insulation, drywall, and ceiling tiles and rework infection prevention barriers on level 8 of Forest A
    • Install utility wiring and framing on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Upcoming Building Care Construction Activities: May 4 to May 10

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 4 to May 10, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Install waterproofing
  • Pour concrete for walls, shafts, slabs, decks and stairs
  • Paint
  • Base framing for connection to River
  • Install anchors for windows
  • Set and weld exterior walls
  • Set up lift system
  • Install glass
  • Set stairs
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical and pneumatic tube blower rooms
  • Install drywall
  • Load in and set air handling units
  • Install fire sprinkler systems
  • Install flooring
  • Demolition for connection points to Forest A
  • Interior activities: install mechanical, electrical, plumbing and drywall in River B patient family lounge; install infection prevention barriers and conduct demolition on lower level 1 of Forest A for building connections

Construction noise will be generated throughout the week. The demolition activities will be the loudest. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.


Building Care Construction Site Closure Extended

The temporary closure of the Building Care construction site has been extended in accordance with the Governor’s “Stay Home, Stay Healthy” emergency order. Limited staff will be onsite to ensure the job site remains secure during this time.

Please call 206-987-8000 or email [email protected] with questions.


Building Care Construction Site Closed March 25 to April 7

From March 25 to April 7 the Building Care construction site will be closed for work. The contractor working on the building has decided to temporarily pause construction out of an abundance of caution to keep their workers safe during the COVID-19 response. Limited staff will be onsite to ensure the worksite remains secure during this time. Work is planned to resume onsite on Wednesday, April 8.

Please call 206-987-8000 or email [email protected] with questions.

 


Upcoming Building Care Construction Activities: Nov. 11 to Nov. 17

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 11 to Nov. 17, construction crews are scheduled to perform the following activities:

  • Install rebar and pour concrete for walls, footings, slabs, and curbs
  • Strip concrete
  • Install waterproofing for walls
  • Install steel forms
  • Prep work on electricity transformer vault
  • Install mechanical, electrical and plumbing
  • Demolish concrete walkways within site
  • Excavation
  • Activities on River C, level 7: construct walls
  • Internal activities: install new pipe and wiring pathways on Forest A, level 1

Construction noise will be generated throughout the week. The loudest activity will be the demolition of concrete walkways within the site. Expect heavy truck traffic, primarily from concrete trucks. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.