Building Care

Category

Upcoming Building Care Construction Activities: April 8 to April 14

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 8 to April 14, construction crews are scheduled to perform the following activities:

  • Drill new piles
  • Demolish some existing piles
  • Excavation
  • Install tie backs/anchors for retaining walls
  • Back fill certain excavated areas
  • Install rebar and stair embeds
  • Internal activities on L1 of Forest A (Friends of Costco Building): install hangers and pipes for multiple systems; install new infection prevention barriers; install new pipe pathways; install firestops

Construction noise will be generated throughout the week. The noisiest external work will be drilling new piles and demolishing some existing piles, which will take place all week. The noisiest internal work will be the installation of new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Wood-Chipping March 26 at Hospital

Wood-chipping will occur at the hospital campus on Tuesday, March 26 within the Building Care construction area. The chipping will generate normal levels of construction noise all day.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: April 1 to April 7

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 1 to April 7, construction crews are scheduled to perform the following activities:

  • Load out current crane from site and load in new crane
  • Excavation
  • Install tie backs/anchors for retaining walls
  • Form concrete slab on grade and wall
  • Internal activities on L1 of Forest A (Friends of Costco Building): core drilling; install pipes, seismic restraints, firestops and hangers for multiple systems; install new pipe pathways; remove infection prevention barrier

The work to load out the current crane and load in the new crane will begin at 5 a.m. on Friday, April 5. The loading and unloading will take place within an existing no parking zone on 40th Avenue NE between NE 45th Street and Sand Point Way NE. This work is occurring early to minimize traffic impacts from the oversize load.

Construction noise will be generated throughout the week. The noisiest external work will be the crane load-out and load-in the morning of April 5 and installing tie backs/anchors, which will take place all week. The noisiest internal work will be the core drilling and installing new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work (other than the crane load-out and load-in discussed above) will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 25 to March 31

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 25 to March 31, construction crews are scheduled to perform the following activities:

  • Excavation
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Form and pour concrete wall
  • Internal activities on L1 of Forest A (Friends of Costco Building): install hangers, pipes, firestops and seismic restraints for multiple systems; replace ceiling grid and tiles; install infection prevention barriers; install new pipe pathways

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors, which will take place all week. The noisiest internal work will be associated with installing new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 18 to March 24

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 18 to March 24, construction crews are scheduled to perform the following activities:

  • Excavation
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Form and pour concrete footing and wall
  • Internal activities on L1 of Forest A: install hangers, pipes, firestops and seismic restraints for multiple water and air systems; core drilling in Forest stairwell #1; install infection prevention barriers; pour equipment pads

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors, which will take place all week. The noisiest internal work will be the core drilling.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 11 to March 17

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 11 to March 17, construction crews are scheduled to perform the following activities:

  • Excavation
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Pour and strip concrete retaining wall
  • Internal activities in Forest A: fire pump replacement work; demolition; install new fire sprinkler valves; saw cutting for reroute of ducts; demolish existing ducts; welding; install infection prevention barriers; core drilling; reframe walls in stairwell 1; install firestops; install new electrical pathways; pour equipment pads

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors, which will take place all week. The noisiest internal work will be the core drilling and demolition.

Expect heavy truck traffic all week as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 4 to March 10

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 4 to March 10, construction crews are scheduled to perform the following activities:

  • Drill piles
  • Excavation
  • Install water treatment pipes
  • Install “lagging” to prevent cave-ins during earthwork
  • Install tie backs/anchors for retaining walls
  • Form, pour and strip concrete; install rebar
  • Patch asphalt
  • Internal activities: fire pump replacement work (including demolition and removal of existing pump and slab); begin Forest service elevator ceiling demolition (install scaffolding, temporary lights and alarms, infection prevention barriers, fire sprinklers and temp power); install scaffolding and infection prevention barriers at Forest Stairwell 1; install pipes, firestops and seismic restraints for emergency oxygen system; core penetrations

Construction noise will be generated throughout the week. The noisiest work will be drilling for the piles and installing tie backs/anchors, both of which will take place all week. The asphalt patching is scheduled for Monday, March 4 and will produce minor odors.

Expect heavy truck traffic all week as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday, except that certain activities inside Forest A associated with replacing the fire pump will occur on Sunday, March 10.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Feb. 25 to March 3

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Feb. 25 to March 3, construction crews are scheduled to perform the following activities:

  • Drill piles
  • Install water treatment pipes
  • Form, pour and strip concrete; install rebar and grating
  • Install “lagging” to prevent cave-ins during earthwork
  • Backfill some excavated areas
  • Install duct banks for pipes and conduits
  • Prepare dirt pads for drill rigs
  • Excavation
  • Install tie backs/anchors for retaining walls
  • Patch asphalt
  • Internal activities: install pipes, valves, dampers and hangers; core drilling

Construction noise will be generated throughout the week. The noisiest work will be drilling for the piles and installing tie backs/anchors, both of which will take place all week. The asphalt patching is scheduled for Friday, March 1 and will produce minor odors.

Expect heavy truck traffic all week as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Feb. 18 to Feb. 24

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Feb. 18 to Feb. 24, construction crews are scheduled to perform the following activities:

  • Install “lagging” to prevent cave-ins during earthwork and backfill excavated areas
  • Install tie backs/anchors for retaining walls
  • Excavation
  • Drill Piles
  • Install duct banks for pipes and conduits
  • Install rebar; form and pour concrete
  • Grading activities
  • Utilities: install stormwater and sewer lines; tap water main in 40th Avenue NE and set water meter
  • Internal activities: replace valves; replace fire pump; install pipes, firestops and seismic restraints; pressure testing

Construction noise will be generated throughout the week. The noisiest work will be drilling for the piles and installing tie backs/anchors, both of which will happen all week. Expect heavy truck traffic all week as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday, except that certain internal activities associated with replacing the fire pump will occur on Sunday, Feb. 24 between 9 a.m. and 6 p.m.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Feb. 11 to Feb. 17

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Feb. 11 to Feb. 17, construction crews are scheduled to perform the following activities:

  • Form and pour concrete curbs
  • Prepare dirt pads for drill rigs
  • Drill piles
  • Excavation
  • Install “lagging” to prevent cave-ins during earthwork and backfill excavated areas
  • Install tie backs/anchors for retaining walls
  • Internal activities: replace valves; core drilling; plumbing and pipe installation; install pipe hangers, firestop systems and seismic restraints; pressure testing
  • Install duct bank (conduits)

Construction noise will be generated throughout the week. The noisiest work will be drilling for the piles, which will occur all week. Expect heavy truck traffic all week as excavated soil is hauled away from the site.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.