Building Care

Category

Upcoming Building Care Construction Activities: Aug. 17 to Aug. 23

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 17 to Aug. 23, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install pneumatic tube stations
  • Core drilling
  • Install insulation
  • Install flooring
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, install ceiling grid, install drywall, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install flooring, paneling, and doors in new chapel location on River A level 7
    • Install utility wiring and paint in conference rooms on Forest A level 2
  • Building connection work:
    • Remove infection prevention barriers on lower level 1 of Forest A
    • Set up infection prevention barriers on level 1 of Forest A
    • Set up infection prevention barriers and begin demolition on level 2 of Forest A
    • Demolition and install steel on level 3 of Forest A
    • Set walls and install seismic joints on level 4 of Forest A
    • Install seismic joints, install utility wiring, install pneumatic tube connections, and framing on level 5 of Forest A
    • Complete framing and install mechanical, electrical, plumbing, and insulation on level 6 of Forest A
    • Install mechanical, electrical, and plumbing connections and complete framing on level 7 of Forest A
    • Install insulation, drywall, and ceiling tiles and rework infection prevention barriers on level 8 of Forest A
    • Install utility wiring and framing on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: May 4 to May 10

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 4 to May 10, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Install waterproofing
  • Pour concrete for walls, shafts, slabs, decks and stairs
  • Paint
  • Base framing for connection to River
  • Install anchors for windows
  • Set and weld exterior walls
  • Set up lift system
  • Install glass
  • Set stairs
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical and pneumatic tube blower rooms
  • Install drywall
  • Load in and set air handling units
  • Install fire sprinkler systems
  • Install flooring
  • Demolition for connection points to Forest A
  • Interior activities: install mechanical, electrical, plumbing and drywall in River B patient family lounge; install infection prevention barriers and conduct demolition on lower level 1 of Forest A for building connections

Construction noise will be generated throughout the week. The demolition activities will be the loudest. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Building Care Construction Site Closure Extended

The temporary closure of the Building Care construction site has been extended in accordance with the Governor’s “Stay Home, Stay Healthy” emergency order. Limited staff will be onsite to ensure the job site remains secure during this time.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Building Care Construction Site Closed March 25 to April 7

From March 25 to April 7 the Building Care construction site will be closed for work. The contractor working on the building has decided to temporarily pause construction out of an abundance of caution to keep their workers safe during the COVID-19 response. Limited staff will be onsite to ensure the worksite remains secure during this time. Work is planned to resume onsite on Wednesday, April 8.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.

 


Upcoming Building Care Construction Activities: Nov. 11 to Nov. 17

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 11 to Nov. 17, construction crews are scheduled to perform the following activities:

  • Install rebar and pour concrete for walls, footings, slabs, and curbs
  • Strip concrete
  • Install waterproofing for walls
  • Install steel forms
  • Prep work on electricity transformer vault
  • Install mechanical, electrical and plumbing
  • Demolish concrete walkways within site
  • Excavation
  • Activities on River C, level 7: construct walls
  • Internal activities: install new pipe and wiring pathways on Forest A, level 1

Construction noise will be generated throughout the week. The loudest activity will be the demolition of concrete walkways within the site. Expect heavy truck traffic, primarily from concrete trucks. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Oct. 14 to Oct. 20

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Oct. 14 to Oct. 20, construction crews are scheduled to perform the following activities:

  • Fire lane expansion activities near NE 45th Street: remove landscaping, clear work area, demolition, grading, install block wall, remove light poles and bollards (a vacuum truck will be used for this work)
  • Activities south of Forest A (near the loading dock and 40th Avenue NE): restore landscaping
  • Install rebar and pour concrete for walls, footings, columns, and slabs
  • Install metal panels and external finish material on exterior mock-up
  • Strip concrete
  • Install waterproofing
  • Drilling into existing electrical vault
  • Excavation
  • Set new underground vault
  • Activities on River level 7: frame and install walls at skybridge connection point
  • Internal activities: reconfigure existing fire equipment on Forest A level 1

Construction noise will be generated throughout the week. The loudest activities will be the demolition associated with the fire lane expansion, including the use of a vacuum truck. Expect heavy truck traffic, primarily from concrete trucks. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 15 to July 21

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 15 to July 21, construction crews are scheduled to perform the following activities:

  • Install rebar and pour concrete for curbs, walls, footings, columns, and pads/slabs
  • Install framing, sheeting, seismic joint, flashing and windows for exterior mock-up
  • Install drains, plumbing and electrical
  • Backfill excavated areas
  • Install scaffold
  • Install waterproofing for walls
  • Form pilaster
  • Activities south of Forest A (near the loading dock and NE 45th Street): excavation; install “lagging” to prevent cave-ins during earthwork; grade for footing; install rebar
  • Internal and external activities on River level 6: remove ceiling tiles; core drill for new vent location; move vent piping; patch roofing
  • Internal and external activities on River level 7: demolish siding; relocate downspout; saw cut and demolish parapet; drill and install rebar
  • Internal activities on L1 of Forest A (Friends of Costco Building): install seismic restraints; replace ceiling

Construction noise will be generated throughout the week. The noisiest external activities will be the concrete work, which will occur all week. The noisiest internal work will be the drilling. Expect heavy truck traffic, primarily from concrete trucks. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: May 27 to June 2

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 27 to June 2, construction crews are scheduled to perform the following activities:

  • Connect to water main in 40th Avenue NE
  • Excavation
  • Set temporary power shed, pull wires, and energize
  • Install rebar and pour concrete for walls and footings
  • Set placing boom mast for tower crane
  • Install tie backs/anchors for retaining walls
  • Install “lagging” to prevent cave-ins during earthwork
  • Install underground pipes
  • Install underground utility vaults; backfill
  • Internal activities on L1 of Forest A (Friends of Costco Building): tie-in work for medical vacuum system

During the water connection work, 40th Avenue NE will be narrowed to one lane, and parking will not be allowed on the west side of the street near Sand Point Way NE and the old Wells Fargo building. Flaggers will be used for traffic control. These impacts will occur during standard construction hours on May 28 and May 29.

Construction noise will be generated throughout the week. The noisiest external work will be installing tie backs/anchors, which is scheduled for the entire week, and the work in 40th Avenue for the water connection, which is scheduled for May 28 and May 29.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: April 8 to April 14

Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 8 to April 14, construction crews are scheduled to perform the following activities:

  • Drill new piles
  • Demolish some existing piles
  • Excavation
  • Install tie backs/anchors for retaining walls
  • Back fill certain excavated areas
  • Install rebar and stair embeds
  • Internal activities on L1 of Forest A (Friends of Costco Building): install hangers and pipes for multiple systems; install new infection prevention barriers; install new pipe pathways; install firestops

Construction noise will be generated throughout the week. The noisiest external work will be drilling new piles and demolishing some existing piles, which will take place all week. The noisiest internal work will be the installation of new pipe pathways.

Expect heavy truck traffic as excavated soil is hauled away from the site. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Wood-Chipping March 26 at Hospital

Wood-chipping will occur at the hospital campus on Tuesday, March 26 within the Building Care construction area. The chipping will generate normal levels of construction noise all day.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.