Construction crews will clean and inspect a newly-installed stormwater drain with a vacuum truck and a camera truck on Thursday, Jan. 24 from 8 to 11 a.m. The trucks will access the site via the paved fire lane that connects to NE 45th Street and runs between the Forest and River buildings. Spotters will be used for pedestrian safety at NE 45th Street and within Seattle Children’s property.
This work will occur outside the fenced construction area, and the vacuum truck will be noisy. Please call 206-987-8000 or email construction@seattlechildrens.org if you have questions.
Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 28 to Feb. 3, construction crews are scheduled to perform the following activities:
- Helen Lane work (near the River entrance): install conduits and wiring, backfill, and set new light poles
- Install power to site office conference trailer
- Install pipes for water treatment
- Demolish, saw cut and remove asphalt
- Prepare dirt pads for drill rigs
- Drill piles
- Stairway north of Forest A: install “lagging” to prevent cave-ins during earthwork and backfill excavated areas
- Internal activities: plumbing and piping; core drilling
Construction noise will be generated throughout the week. The noisiest work will be the drilling for the piles (scheduled for Jan. 25 to Feb. 13) and the asphalt demolition and saw cutting, which will take place Jan. 28 and Jan. 29.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
On Saturday, Jan. 19, construction crews will take down the final tower crane on the Building Cure site. Crews will begin staging at 2 a.m. and the mobile crane needed to dismantle the tower crane will arrive at 4:30 a.m. Dismantling will begin at 7:15 a.m. and should be complete by 8 p.m.
On Sunday, Jan. 20, crews will begin work at 8 a.m. to hoist the rooftop chillers into place. This work will finish around 4 p.m.
All work will be done from within the jobsite fence except for intermittent traffic entering and exiting the site.
Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 21 to Jan. 27, construction crews are scheduled to perform the following activities:
- Helen Lane work (near the River entrance): demolish and remove existing lighting, excavate for light pole bases, and install light pole bases
- Cap pipes at sediment ponds on Sand Point Way
- Utilities: cut and cap existing stormwater pipes; install new stormwater pipes
- Prepare dirt pad for drill rig
- Stairway north of Forest A: install rebar; pour, strip and waterproof a new concrete wall; install “lagging” to prevent cave-ins during earthwork
- Drill foundation piles
- Internal activities: plumbing and piping for emergency oxygen system
- Shoring contractor mobilizes to the Building Care site
Construction noise will be generated throughout the week. The noisiest work will be the drilling for the foundation piles (scheduled for Jan. 25 to Jan. 31) and the excavation for the light pole bases on Helen Lane, which will require a vacuum truck on Saturday, Jan. 26.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Beginning Jan. 14, Terry Avenue, between Stewart and Virginia Streets, will be closed to vehicular traffic to construct the new Terry Avenue Green Street. The closure is expected to last through May 2019. During this time we will construct new sidewalks, repave to add access points/drop-off zones, create new planter beds and landscaping, and add a number of pedestrian benches and activation points. Throughout construction activities, pedestrian access will be maintained on one side of Terry Avenue. Please follow all street and sidewalk closed signs and pedestrian diversions, as they are in place for your safety.
Also beginning Jan. 14, normal working hours at Building Cure shift so all work and deliveries begin at 6 a.m. This will last for the duration of the viaduct closure. The exception is civil work on Terry Avenue, which will begin at 7 a.m.
Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 14 to Jan. 20, construction crews are scheduled to perform the following activities:
- Build deck and stairs for new site office conference trailer
- Install power pumps for water treatment
- Saw cut, demolish and remove existing asphalt
- Excavate for site temporary power and install duct bank (conduits)
- Utilities: cut and cap existing storm lines; install power meter; Seattle City Light to install power service; cut and remove existing stormwater shoring; excavate for storm drain brackets
- Prepare dirt pad for drill rig
- Form, pour and strip concrete at stairway north of Forest A; install rebar; set concrete wall form
Construction noise will be generated throughout the week. The noisiest work will be the asphalt demolition and saw cutting, which is scheduled for Jan. 15 and Jan. 16.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 7 to Jan. 13, construction crews are scheduled to perform the following activities:
- Set up site office conference trailer; build deck and stairs
- Excavate, form and pour trench drains
- Install cladding on ED canopy
- Demolish existing concrete stairs, footings and the old helipad
- Utilities: pull electrical wire; install conduits; install stormwater and water lines; remove existing catch basins and pipes
- Excavate for new stair footings
- Patch asphalt
- Backfill excavated areas
- Install waterproofing on new stairs
- Install concrete rip rap
Construction noise will be generated throughout the week. The noisiest work will be the demolition, which is scheduled from Jan. 4 to Jan. 10. The asphalt patching will produce some odor on Jan. 8 (date subject to change depending on the weather).
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 31 to Jan. 6, construction crews are scheduled to perform the following activities:
- Set up site office conference trailer
- Forest staff entrance: remove temporary overhead protection and touch up paint
- Finish installing temporary dust containment wall at the Emergency Department (ED)
- ED canopy: install framing, sheeting and cladding on canopy
- Backfill multiple excavated areas
- Drill concrete and install rebar on the north side of Forest A
- Form, pour and strip concrete wall at stairway north of Forest A and around tree relocation island
- Utilities: install power, water, stormwater and sewer pipes; set catch basins; tap water main and set water meter
- Patch asphalt
- Install concrete rip rap
Construction noise will be generated throughout the week. The noisiest work will be the concrete drilling, which is scheduled from Dec. 27 to Dec. 31. The asphalt patching will produce some odor on Dec. 31 (date subject to change depending on the weather).
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. Work will not occur on Sunday or on Tuesday, Jan. 1.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 24 to Dec. 30, construction crews are scheduled to perform the following activities:
- Install black mesh screening on the construction fence
- Remove existing stone
- Remove temporary walls at the Forest staff entrance
- Install temporary dust containment wall at the ED
- ED canopy: install support steel, then install framing and sheeting on the canopy
- Backfill excavated areas
- Demolish existing concrete stairs and footings
- Drill concrete and install rebar
- Utilities: install water treatment and stormwater pipes; set catch basins; install sleeves and box for natural gas (Puget Sound Energy)
Construction noise will be generated throughout the week. The noisiest work will be the demolition and the concrete drilling; the demolition is scheduled to take place from Dec. 24 to Dec. 28, while the drilling is scheduled from Dec. 27 to Dec. 31.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. Work will not occur on Sunday or on Tuesday, Dec. 25.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. From now until building opening in Spring 2022, there will be ongoing construction activity at the hospital campus. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 17 to Dec. 23, construction crews are scheduled to perform the following activities:
- Install black mesh screening on the construction fence
- Place asphalt for temporary construction roads and around a relocated tree island within the site (asphalt placement is weather-dependent)
- Set up steel containment tanks for water treatment
- Remove existing stone
- Sawcut concrete footings
- Install framing support steel and a temporary dust containment wall for the Emergency Department canopy
- Form and pour concrete curbs, footings, and walkways
- Install prefabricated vestibule panels at the Forest A staff entrance
- Utilities: clearing and grubbing; install sewer and stormwater pipes; set catch basins
- Demolish existing concrete stairs and footings
- Excavate and run conduit for temporary power
While construction noise will be generated throughout the week, the noisiest work will be the demolition, which is scheduled to take place from Dec. 20 to Dec. 28. The asphalt placement is scheduled for Dec. 17 and Dec. 20 and will create some odor; please note the asphalt placement depends on the weather, so the dates listed here are subject to change.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. Work will not occur on Sunday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.