Seattle Children’s Hospital Campus

Category

Upcoming Building Care Construction Activities: July 13 to July 19

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 13 to July 19, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Framing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Power vault buildout by Seattle City Light
  • Interior activities: relocate vending machines to new location on River B level 3; install drywall for new chapel location on River A level 7; install insulation and drywall in lower level 1 of Forest A for future connections; set up infection prevention barrier on level 7 of Forest A for future connections; demolish existing ceiling tiles, rework plumbing and install steel on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: July 6 to July 12

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From July 6 to July 12, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, and pads
  • Install fireproofing
  • Paint
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Load in and set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Install soil
  • Interior activities: install drywall, insulation, and mechanical, electrical and plumbing for new chapel location on River A level 7; install mechanical, electrical and plumbing in lower level 1 of Forest A for future connections; set up infection prevention barriers and demolish existing ceiling tiles on level 8 of Forest A for future connections

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 29 to July 5

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 29 to July 5, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Install pneumatic tube system
  • Load in and set air handling units
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Install soil
  • Interior activities: frame walls and install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The job site will be closed Saturday, July 4, for Independence Day.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Street Parking East of the Hospital Campus – Update

At the end of March, the City of Seattle implemented a temporary suspension of Seattle Children’s employee parking restrictions near the hospital campus and reserved several streets east of the hospital campus to support Children’s essential health care workers responding to the COVID-19 public health crisis. This week, the Seattle Department of Transportation will be returning these previously reserved streets to public use and will remove the “Reserved for hospital employees only” signs.

For questions, please call 206-987-8000 or email construction@seattlechildrens.org.


Upcoming Building Care Construction Activities: June 22 to June 28

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 22 to June 28, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Install air flow louvers
  • Set rooftop chillers
  • Install glass
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems and alarm controls
  • Install flooring
  • Install pneumatic tube system
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Interior activities: install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


40th Avenue NE Pavement Restoration – Work Extension

Due to the recent wet weather, the pavement restoration work in 40th Avenue NE being performed by Puget Sound Energy (PSE) will extend into the week of June 15. This work is occurring between Seattle Children’s Emergency Department (ED) driveways and Sand Point Way NE; it is temporarily affecting some on-street parking north of the ED driveways, but two lanes of travel are being maintained. PSE has informed us that they expect to complete the work on Monday, June 15, but since the project is weather-dependent, the weather conditions will determine exactly when the work can be completed. All pavement restoration activities will take place between 9 a.m. and 3 p.m. daily.


Upcoming Building Care Construction Activities: June 15 to June 21

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 15 to June 21, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls, shafts, slabs, curbs and pads
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Set up lift system
  • Set rooftop chillers
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Install drywall
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Seattle City Light vault buildout
  • Interior activities: install mechanical, electrical and plumbing for new chapel location on River A level 7; install connections for mechanical, electrical and plumbing in lower level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


40th Avenue NE Pavement Restoration Begins June 8

Beginning Monday, June 8, Puget Sound Energy will restore the pavement within 40th Avenue NE between Seattle Children’s Emergency Department (ED) driveways and Sand Point Way NE. This work will temporarily affect some on-street parking north of the ED driveways, but two lanes of travel will be maintained. Flaggers will assist with traffic control. This restoration work is expected to last approximately one week and will take place between 9 a.m. and 3 p.m. daily.


Upcoming Building Care Construction Activities: June 8 to June 14

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 8 to June 14, construction crews are scheduled to perform the following activities:

  • Erect cladding and support steel
  • Pour concrete for walls, shafts, slabs, pads, curbs and decks
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install roofing
  • Set rooftop chillers
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Install exterior sheeting
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Interior activities: paint and clean on River B level 3 for new vending machines location; demolish walls and install mechanical, electrical and plumbing for new chapel location on River A level 7.

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: June 1 to June 7

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From June 1 to June 7, construction crews are scheduled to perform the following activities:

  • Erect cladding and support steel
  • Pour concrete for walls, shafts, slabs, pads, curbs and decks
  • Install fireproofing
  • Paint
  • Install anchors and clips for windows
  • Set and weld exterior walls
  • Install temporary roofing
  • Install mechanical and electrical roofing supports
  • Install glass
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install insulation
  • Install fire sprinkler systems
  • Install flooring
  • Install exhaust air, plumbing and medical gas risers
  • Set air handling units and supports
  • Interior activities: install mechanical, electrical, plumbing and drywall on River B level 3 for new vending machines location; set up infection prevention barriers and demolish ceiling for new chapel location on River A level 7.

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.