Seattle Children’s Hospital Campus

Category

Upcoming Building Care Construction Activities: May 10 to May 16

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 10 to May 16, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Install asphalt
  • Install glass at canopy and vestibule
  • Paint
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install ceilings
  • Install flooring
  • Form and pour concrete stairs and walkways
  • Demolish asphalt and concrete
  • Install irrigation
  • Install topsoil
  • Saw cut concrete and asphalt
  • Building connection work:
    • Set up infection prevention barriers and demolish walls, ceilings, and plumbing on level 3 of River C
    • Paint and install flooring, windows, and siding on level 1 of Forest A

Construction noise will be generated throughout the week. The saw cutting and demolishing of asphalt and concrete will generate the most noise. The asphalt installation will generate some odors. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: May 3 to May 9

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 3 to May 9, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Install asphalt
  • Remove scaffolding
  • Install glass canopy
  • Paint
  • Install metal sheeting and panels
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install ceilings
  • Install flooring
  • Form and pour concrete stairs and new Emergency Department entry drive
  • Demolish asphalt and concrete
  • Install irrigation
  • Grading
  • Saw cut concrete and asphalt
  • Building connection work:
    • Remove infection prevention barriers on level 3 of River C
    • Frame walls and ceilings; install utility wiring and siding on level 1 of Forest A

Construction noise will be generated throughout the week. The saw cutting and demolishing of asphalt and concrete will generate the most noise. The asphalt installation will generate some odors. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: April 26 to May 2

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 26 to May 2, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Remove scaffolding
  • Paint
  • Install metal sheeting and panels
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install ceilings
  • Install flooring
  • Form and pour concrete slabs, stairs, and walkway
  • Demolish asphalt and concrete
  • Excavation
  • Install oxygen line (near Emergency Department entrance)
  • Grading
  • Saw cut concrete and asphalt
  • Building connection work:
    • Demolish walls, floors, and ceilings; install utility wiring, windows, and siding on level 1 of Forest A

Construction noise will be generated throughout the week. The saw cutting and demolishing of asphalt and concrete will generate the most noise. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Early Morning Equipment Removal at Building Care Site, April 19

On Monday, April 19, a truck and semi-trailer will arrive at the Building Care construction site at approximately 5:30 a.m. to load and remove a large trackhoe. The truck will enter and exit the site via the construction entrance on Sand Point Way NE. We do not expect this activity to produce substantial noise, but neighbors across Sand Point Way may be able to hear backup beepers from the truck and the trackhoe. Crews will perform this work as quickly as possible, and the truck is expected to depart prior to 6 a.m. This activity needs to occur early because the city requires oversize loads to be off the streets by 6 a.m.

Please call 206-987-8000 or email construction@seattlechildrens.org if you have questions.


Tree Work at Hospital Campus, April 23

On Friday, April 23, Bartlett Tree Experts will prune a damaged tree and a hedge on the west side of the hospital campus near Sand Point Way NE, between Penny Drive and the construction entrance. This work will occur between 8 a.m. and 3 p.m. The crew will use chainsaws and chippers, which will generate noise. We do not anticipate any transportation impacts on Sand Point Way or the adjacent sidewalk.

If you have questions, please contact Meghan Fuller, manager of Grounds Maintenance, at 206-307-6687.


Upcoming Building Care Construction Activities: April 19 to April 25

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 19 to April 25, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Paint
  • Install metal sheeting and panels
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install ceilings
  • Install flooring
  • Pressure washing
  • Form and pour concrete slabs, stairs, and walls
  • Demolish asphalt and concrete
  • Excavation
  • Vacuum truck on-site for oxygen line (near Emergency Department entrance)
  • Install soil
  • Grading
  • Building connection work:
    • Remove infection prevention barriers on level 7 of River C
    • Demolish walls, floors, and ceilings; install seismic joint on level 1 of Forest A

Construction noise will be generated throughout the week. A vacuum truck, which will generate additional noise, will be on-site near the Emergency Department entrance on 40th Avenue NE on April 21 and 22. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Tree Work at Hospital Campus, April 15

On Thursday, April 15, Bartlett Tree Experts will prune and remove hazardous trees between the Ocean parking garage and 45th Avenue NE. This work will occur between 8 a.m. and 3 p.m. The crew will use chainsaws and chippers, which will generate noise. We do not anticipate any transportation or parking impacts on 45th Avenue. The tree work is preventative landscaping maintenance and not related to any construction activity at the hospital campus.

If you have questions, please contact Meghan Fuller, manager of Grounds Maintenance, at 206-307-6687.


Upcoming Building Care Construction Activities: April 12 to April 18

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 12 to April 18, construction crews are scheduled to perform the following activities:

  • Special note: On April 9, we will begin the first phase of reconfiguring the Emergency Department (ED) drop-off and drive aisle. The ED vehicular entrance will remain in the same location for now, but ED vehicles will no longer exit onto 40th Avenue NE; instead, they will be routed north through the hospital campus.
  • Build out interior spaces
  • Paint
  • Install metal sheeting and panels
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install ceilings
  • Install flooring
  • Install roofing
  • Pressure washing
  • Form and pour concrete slabs, stairs, and walls
  • Demolish asphalt, concrete, lights, and signage at ED drop-off area
  • Install irrigation
  • Building connection work:
    • Paint; install doors and signage; and cleaning on level 3 of River C
    • Paint, install signage, move infection prevention barrier, and cleaning on level 7 of River C
    • Install seismic joint and fire proofing on level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: April 5 to April 11

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From April 5 to April 11, construction crews are scheduled to perform the following activities:

  • Special note: On April 8, we will begin the first phase of reconfiguring the Emergency Department (ED) drop-off and drive aisle. The ED vehicular entrance will remain in the same location for now, but ED vehicles will no longer exit onto 40th Avenue NE; instead, they will be routed north through the hospital campus.
  • Build out interior spaces
  • Framing
  • Paint
  • Install metal sheeting and panels
  • Install and trim mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install ceilings
  • Install flooring
  • Pressure washing
  • Form and pour concrete slabs
  • Demolish temporary power switchboard and temporary duct bank
  • Building connection work:
    • Paint and install doors and glass on level 3 of River C
    • Install and trim utility wiring, and install ceiling on level 7 of River C
    • Demolish walls, floors and ceilings; install utility wiring; and install windows on level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: March 29 to April 4

There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From March 29 to April 4, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install ceilings
  • Install flooring
  • Pressure washing
  • Form and pour concrete curbs, slabs, and stairs
  • De-energize temporary power and remove temporary power poles (Seattle City Light)
  • Building connection work:
    • Install carpets and doors on level 3 of River C
    • Install wall coverings on level 7 of River C
    • Demolish walls, floors and ceilings; trim utility wiring; and install seismic joint, sheeting, and fireproofing on level 1 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.