Construction Blog

Upcoming Building Care Construction Activities: Jan. 4 to Jan. 10

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Jan. 4 to Jan. 10, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Building connection work:
    • Install utility wiring, insulation, drywall, flooring, and ceiling on level 3 of River C
    • Install metal panels and trim utility wiring on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Dec. 28 to Jan. 3

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 28 to Jan. 3, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Framing
  • Install drywall
  • Install trim
  • Tape and paint
  • Install metal sheeting and panels
  • Install stone cladding on exterior
  • Install mechanical and electrical wiring and plumbing equipment
  • Install sprinkler system
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical and telecommunication rooms
  • Begin Terrazzo flooring install in main entry
  • Building connection work:
    • Install doors, complete soffits and paint on level 3 of River C
    • Cleaning on levels 4 and 5 of River C
    • Final inspections on level 1 of Forest A stair egress; reopen in advance of FA Staff Entrance Closure

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Jan. 1.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Dec. 21 to Dec. 27

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 21 to Dec. 27, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Demolish temporary electrical switchboard
  • Building connection work:
    • Framing and install utility wiring, drywall, and sprinklers on level 3 of River C
    • Paint and relocate infection prevention barriers on level 4 of River C
    • Install signage and relocate infection prevention barriers on level 5 of River C
    • Cleaning on level 6 of River C
    • Install expansion joint cover plates on level 7 of River C
    • Paint, trim utility wiring, and patch flooring on level 1 of Forest A
    • Paint and remove infection prevention barriers on level 3 of Forest A
    • Install expansion joint covers and flooring, and remove infection prevention barriers on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Dec. 25.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Sidewalk Work on NE 50th Street, Dec. 14 and 15

On Monday, Dec. 14, and Tuesday, Dec. 15, construction crews will repair sidewalks and install Americans With Disabilities Act (ADA) ramps in the following location:

  • On the north side of NE 50th Street, between Sand Point Way NE and Sand Point Place NE, from Dec. 14 to Dec. 15.

The sidewalks and street parking in this area will be closed during construction, and pedestrian detour signage will be posted. Trucks will park on the streets, but all traffic lanes will remain open. This work will generate noise, including concrete saw cutting.

All work associated with this project will occur between 8 a.m. and 6 p.m. on weekdays. We expect to complete the project by Dec. 15; however, the construction dates could change based on weather conditions. Once the work is complete, neighbors will benefit from safer sidewalks and more accessible crossings.

If you have questions, please contact Michael Lloyd, Project Manager – Facility Planning, Design & Construction, at 601-527-1317.


Upcoming Building Care Construction Activities: Dec. 14 to Dec. 20

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 14 to Dec. 20, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, and telecommunication rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Remove temporary power poles and demolish temporary duct bank and switchboard pad
  • Building connection work:
    • Framing and install utility wiring on level 3 of River C
    • Install utility wiring and flooring on level 4 of River C
    • Paint and install flooring on level 5 of River C
    • Paint on level 6 of River C
    • Framing and install expansion joint, utility wiring, drywall, and insulation on level 7 of River C
    • Remove infection prevention barriers on level L1 of Forest A
    • Paint, install flooring, and trim utility wiring on level 1 of Forest A
    • Paint, install ceiling, and trim utility wiring on level 3 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Dec. 7 to Dec. 13

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Dec. 7 to Dec. 13, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Waterproofing
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Install utility wiring on level 3 of River C
    • Paint on level 4 of River C
    • Install utility wiring, expansion joint cover plates, and ceiling on level 5 of River C
    • Install flooring on level 6 of River C
    • Paint and remove infection prevention barriers on level L1 of Forest A
    • Paint, install flooring, and trim utility wiring on level 1 of Forest A
    • Remove infection prevention barriers on level 4 of Forest A
    • Paint and install corner guards on level 5 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Nov. 30 to Dec. 6

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 30 to Dec. 6, construction crews are scheduled to perform the following activities:

  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Waterproofing
  • Install siding
  • Install elevator equipment
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Demolish walls and ceiling and install utility wiring on level 3 of River C
    • Paint and install utility wiring and ceiling on level 5 of River C
    • Install expansion joint covers, utility wiring, and ceiling on level 6 of River C
    • Install expansion joint covers on level 7 of River C
    • Paint and install ceiling on level L1 of Forest A
    • Paint and install flooring on level 1 of Forest A
    • Remove infection prevention barriers on level 2 of Forest A
    • Paint, install corner guards, and remove infection prevention barriers on level 3 of Forest A
    • Paint and install ceiling, utility wiring, and corner guards on level 4 of Forest A
    • Paint and install ceiling and utility wiring on level 5 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Nov. 23 to Nov. 29

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 23 to Nov. 29, construction crews are scheduled to perform the following activities:

  • Pour concrete for shafts and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install ductwork
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Demolish walls and ceilings and install support steel on level 3 of River C
    • Paint and install utility wiring and ceiling on level 6 of River C
    • Install door, insulation, and drywall on level 7 of River C
    • Paint and remove infection prevention barriers on level L1 of Forest A
    • Paint and install flooring on level 1 of Forest A
    • Install corner guards and remove infection prevention barriers on level 2 of Forest A
    • Paint, trim utility wiring, and install ceiling and doors on level 3 of Forest A
    • Paint on level 4 of Forest A
    • Paint on level 5 of Forest A
    • Trim utility wiring on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Nov. 26 and 27 for the Thanksgiving holiday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Nov. 16 to Nov. 22

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 16 to Nov. 22, construction crews are scheduled to perform the following activities:

  • Pour concrete for shafts and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Waterproofing
  • Install siding
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Demolish walls and install support steel and utility wiring on level 3 of River C
    • Install expansion joint, utility wiring, insulation, and drywall on level 4 of River C
    • Install drywall on level 5 of River C
    • Air testing, paint, and remove infection prevention barrier on level 6 of River C
    • Framing and install utility wiring, insulation, and expansion joint on level 7 of River C
    • Paint on level L1 of Forest A
    • Paint and install insulation, drywall, and seismic joint covers on level 1 of Forest A
    • Paint and install flooring on level 2 of Forest A
    • Paint, patch ceilings, and trim utility wiring on level 3 of Forest A
    • Install seismic joint covers on level 4 of Forest A
    • Install seismic joint covers on level 5 of Forest A
    • Install metal panels on level 9 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Upcoming Building Care Construction Activities: Nov. 9 to Nov. 15

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Nov. 9 to Nov. 15, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs, shafts and walls
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install elevator equipment
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Install ceilings
  • Build out electrical, mechanical, telecommunication, machine and generator rooms
  • Install flooring
  • Build out interior spaces
  • Install sprinkler system
  • Building connection work:
    • Install infection prevention barriers and demolish ceiling and walls on level 3 of River C
    • Framing and install drywall and utility wiring on level 4 of River C
    • Install expansion joint, utility wiring, and insulation on level 5 of River C
    • Paint and install ceiling, utility wiring, drywall, and expansion joint on level 6 of River C
    • Framing and install utility wiring on level 7 of River C
    • Seal floors and install ceiling on level L1 of Forest A
    • Framing and install utility wiring, drywall, and pneumatic tube connections on level 1 of Forest A
    • Install ceilings, utility wiring, and flooring on level 2 of Forest A
    • Install flooring and seismic joint covers on level 3 of Forest A
    • Install flooring, utility wiring, insulation, drywall, and seismic joint covers on level 4 of Forest A
    • Install flooring and seismic joints on level 5 of Forest A
    • Install corner guards and remove infection prevention barriers on level 6 of Forest A
    • Remove infection prevention barriers on level 7 of Forest A

Construction noise will be generated throughout the week. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.