Neighborhood Contact Line
Downtown Seattle
In downtown Seattle, for Building Cure issues or emergency, please contact us.
In downtown Seattle, for Building Cure issues or emergency, please contact us.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 25 to Jan. 31, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
From Jan. 25 to Feb. 9 a crew will conduct utility potholing along Penny Drive and two locations on NE 50th St near 44th Ave NE. The work is being done to identify utilities under the roadways to support the design for the proposed Surgery Building and Parking Garage.
A vacuum truck and a small crew will work from 7 am to 3:30 pm each day. Construction noise will be generated off and on during this work; noisy activities will not begin before 8 am. Traffic control will be set up around the work zones.
On NE 50th St, the work will require taking one traffic lane to accommodate utility trucks in the street. Parking restrictions will be in place and flaggers will be present during the work to direct drivers and pedestrians around the work zones.
On Penny Drive, two-way traffic will be maintained when possible, but at times Penny Drive will be reduced to one lane. The Mountain Loading Dock, Ocean 7 Staff Entrance and Lot 4 will all be temporarily impacted during this work. Access to Lots 1, 2, 3 and 4 will be maintained at all times. Pedestrians and bikes will be rerouted. Please allow additional time for travel along Penny Drive during this work.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 18 to Jan. 24, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 11 to Jan. 17, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Jan. 4 to Jan. 10, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 28 to Jan. 3, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Jan. 1.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 21 to Dec. 27, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday. The construction site will be closed on Dec. 25.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
On Monday, Dec. 14, and Tuesday, Dec. 15, construction crews will repair sidewalks and install Americans With Disabilities Act (ADA) ramps in the following location:
The sidewalks and street parking in this area will be closed during construction, and pedestrian detour signage will be posted. Trucks will park on the streets, but all traffic lanes will remain open. This work will generate noise, including concrete saw cutting.
All work associated with this project will occur between 8 a.m. and 6 p.m. on weekdays. We expect to complete the project by Dec. 15; however, the construction dates could change based on weather conditions. Once the work is complete, neighbors will benefit from safer sidewalks and more accessible crossings.
If you have questions, please contact Michael Lloyd, Project Manager – Facility Planning, Design & Construction, at 601-527-1317.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 14 to Dec. 20, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.
Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.
From Dec. 7 to Dec. 13, construction crews are scheduled to perform the following activities:
Construction noise will be generated throughout the week. Expect heavy truck traffic. Construction activity is weather-dependent and subject to change based on conditions.
All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.
Please call 206-987-8000 or email construction@seattlechildrens.org with questions.