There will be ongoing construction activity for Building Care at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Sept. 13 to Sept. 19, construction crews are scheduled to perform the following activities:

  • Build out interior spaces
  • Restore sidewalks on Sand Point Way NE and 40th Avenue NE (see separate post from Sept. 1 for more information)
  • Install soil and mulch
  • Plant landscaping
  • Install irrigation

Construction noise will be generated throughout the week. Expect heavy truck traffic. The sidewalk restoration is expected to be the loudest external activity. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email [email protected] with questions.