Seattle Children’s Hospital Campus

Category

Update on Landscaping Maintenance Along 45th Ave NE

Meghan Fuller, manager of the Grounds department, provided the following update on the landscaping work happening along 45th Ave NE.

The area between the Ocean parking garage and 45th Ave NE has been neglected since it was planted in about 2003. If you look from 45th, you’ll see the area is covered with trees – however not one of those trees below the wall was purposely planted; they all blew in as volunteer weed trees. They include cottonwoods, willows, a horse chestnut, quaking aspen, and other trees. They do create a wonderful screen for the neighborhood, however, so that part is a blessing. But unfortunately, the lower area also became filled with dense blackberry – so dense that it has grown up 20+’ in some places, into the trees and to the area above the wall.

Dense blackberry climbs up trees, shades out other plants, and over time kills things trapped underneath it. The area at the north end, above the retaining wall, was so infested that no living plants remained underneath. If you go there now, you’ll notice a large fallen dead pine tree lying on the slope – it’s obviously been there for years, but the blackberry was so incredibly dense and tall, and the area so inaccessible, that we didn’t even know it was in there until we removed the blackberry.

This past Spring, we began the process of renovating the full length of the space above the retaining wall to create a dense but beautiful screen of shrubs and trees for the neighbors.

Here’s a list of what we’re doing:

  1. Cut down blackberries and hand dig out the roots.
  2. Remove ivy off trees, as that also kills them over time.
  3. Remove dead shrubs and trees (we are not removing living plants, just things that are dead or nearly dead).
  4. Have our tree company prune off large dead branches that could be a hazard if they fell.
  5. Mulch the area to prevent weeds and erosion.
  6. This fall, winter, and spring, begin adding trees, shrubs, ferns, and small plants to create a multi-layered canopy and understory of plantings that result in a much more effective visual and sound barrier, not just at the edge of the 45th sidewalk, but across the full depth of the space.
  7. Then we’ll begin clearing & digging the blackberry and dead plants out of the area below the retaining wall. Any hazardous or dead/dying trees will be removed (there are only a few) and the rest of the living trees and shrubs will remain. The area underneath will also be replanted with a mix of trees, shrubs, and understory plantings to add to the visual barrier between the hospital and neighborhood.

Replanting in this area will happen over the next few months to fill in portions of the perimeter where there is visibility to the hospital. To the extent possible, we will select large plants as replacements. Our grounds crew has already installed green landscaping fabric where there are gaps.

As the space comes together and begins to grow in with new plantings, we hope neighbors will be very pleased with it. It is a much-needed improvement that will be designed to last years into the future. Please know that I am very committed to creating and maintaining an effective and beautiful barrier between the hospital and neighborhood – and as a grounds manager, it’s important to me that it’s healthy and sustainable for years to come, and does not include weed infestations, hazardous trees, or areas so dense that they cannot be maintained.


Upcoming Building Care Construction Activities: Oct. 12 to Oct. 18

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Oct. 12 to Oct. 18, construction crews are scheduled to perform the following activities:

  • Pour concrete for slabs and walls
  • Framing
  • Paint
  • Install roofing
  • Set walls
  • Install windows
  • Install metal sheeting and panels
  • Install mechanical and electrical wiring and plumbing equipment
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, machine and generator rooms
  • Install insulation
  • Install flooring
  • Install sprinkler systems
  • Build out interior spaces
  • Set air handling units
  • Electrical power installation (Seattle City Light)
  • Building connection work:
    • Set up infection prevention barriers on level 5 of River C
    • Saw cut concrete, install seismic plate, frame walls, and demolish windows, walls, and ceilings on level 6 of River C
    • Set up infection prevention barriers and start demolition on level 7 of River C
    • Install seismic joint covers and drywall on level L1 of Forest A
    • Install drywall and utility wiring on level 1 of Forest A
    • Set walls on level 2 of Forest A
    • Set walls and install seismic joints on level 3 of Forest A
    • Complete framing and install seismic joints, utility wiring, and pneumatic tube connections on level 4 of Forest A
    • Install utility wiring, insulation, and drywall on level 5 of Forest A
    • Install drywall and seismic joint covers on level 6 of Forest A
    • Trim utility wiring on level 8 of Forest A
    • Install gurneyway connection and drywall on level 9 of Forest A

Construction noise will be generated throughout the week. Internally, the loudest activity will be the demolition and saw cutting on River C levels 6 and 7. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Drill Rig on Hospital Campus from Sept. 21 to Oct. 9

As a part of preliminary work for Project Copper (the proposed surgery pavilion and parking garage) on the hospital campus, a geotechnical consultant will be onsite to collect soil samples using a drill rig. The work is scheduled for approximately three weeks between Sept. 21 to Oct. 9 and will be done during regular work hours, 8 a.m. to 5 p.m. weekdays. Soil samples will be collected in Lot 4 and near the Ocean 7 staff entrance.

Construction noise will be generated during this work. The impact to neighbors is expected to be minimal; staff and patient families will likely hear the most noise. Expect to see large trucks and heavy equipment onsite, with some parking restrictions in Lot 4 during this work. Construction activity is weather-dependent and subject to change based on conditions.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Tree Work at Hospital Campus, Sept. 14 to Sept. 18

Tree Work at Hospital Campus, Sept. 14 to Sept. 18

Bartlett Tree Experts is scheduled to perform tree work at the Seattle Children’s hospital campus from Monday, Sept. 14, to Friday, Sept. 18. The work includes removing trees that are dying or hazardous, pruning healthy trees to remove dead or low branches, and removing branches leaning on structures.

Activities will take place throughout the hospital campus, including along the perimeters. Bucket trucks will temporarily park on the south side of NE 50th Street, the west side of 45th Avenue NE, and the north side of NE 45th Street. We do not expect any traffic impacts; the sidewalks, however, will be closed in those areas while work is underway.

Crews will use chainsaws and chippers, which will generate noise, each day from 8 a.m. to 2:30 p.m. We expect this work will have minimal impact on the perimeter tree buffer.

If you have questions, please contact Meghan Fuller, manager of Grounds Maintenance, at 206-307-6687.


Upcoming Building Care Construction Activities: Aug. 17 to Aug. 23

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From Aug. 17 to Aug. 23, construction crews are scheduled to perform the following activities:

  • Pour concrete for walls and shafts
  • Install fireproofing
  • Framing
  • Paint
  • Install roofing
  • Install windows
  • Install metal sheeting
  • Install elevator equipment
  • Install mechanical and electrical wiring and plumbing equipment
  • Set air handling units
  • Install drywall
  • Install siding
  • Build out electrical, mechanical, generator and pneumatic tube blower rooms
  • Install pneumatic tube stations
  • Core drilling
  • Install insulation
  • Install flooring
  • Build out interior spaces
  • Work in existing buildings:
    • Install utility wiring and pipes, install ceiling grid, install drywall, and paint on River B level 3 in old vending machine location for Starbucks coffee cart
    • Install flooring, paneling, and doors in new chapel location on River A level 7
    • Install utility wiring and paint in conference rooms on Forest A level 2
  • Building connection work:
    • Remove infection prevention barriers on lower level 1 of Forest A
    • Set up infection prevention barriers on level 1 of Forest A
    • Set up infection prevention barriers and begin demolition on level 2 of Forest A
    • Demolition and install steel on level 3 of Forest A
    • Set walls and install seismic joints on level 4 of Forest A
    • Install seismic joints, install utility wiring, install pneumatic tube connections, and framing on level 5 of Forest A
    • Complete framing and install mechanical, electrical, plumbing, and insulation on level 6 of Forest A
    • Install mechanical, electrical, and plumbing connections and complete framing on level 7 of Forest A
    • Install insulation, drywall, and ceiling tiles and rework infection prevention barriers on level 8 of Forest A
    • Install utility wiring and framing on level 9 of Forest A

Construction noise will be generated throughout the week. The fireproofing will generate some odors. Expect heavy truck traffic, primarily for concrete and material deliveries. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Street Parking East of the Hospital Campus – Update

At the end of March, the City of Seattle implemented a temporary suspension of Seattle Children’s employee parking restrictions near the hospital campus and reserved several streets east of the hospital campus to support Children’s essential health care workers responding to the COVID-19 public health crisis. This week, the Seattle Department of Transportation will be returning these previously reserved streets to public use and will remove the “Reserved for hospital employees only” signs.

For questions, please call 206-987-8000 or email construction@seattlechildrens.org.


Tree Removal and Stormwater Work to Continue Next Week

From Monday, May 4 to Thursday, May 7, a crew will continue work to repair a broken stormwater pipe at the north end of the hospital campus, near NE 50th Street. This work will require the removal of some trees. Noise from excavators, chainsaws and wood chippers will be generated between 8 a.m. and 6 p.m. on those days. Please contact Meghan Fuller, manager of Grounds Maintenance, at 206-307-6687 if you have questions.


Upcoming Building Care Construction Activities: May 4 to May 10

Building Care construction is underway. There will be ongoing construction activity at the hospital campus until the building opens in spring 2022. Seattle Children’s will publish a weekly post on this Construction Blog that outlines the work expected to occur the following week. We will also post to this blog whenever a construction activity will be especially impactful to neighbors.

From May 4 to May 10, construction crews are scheduled to perform the following activities:

  • Erect structural and support steel
  • Install decking
  • Install waterproofing
  • Pour concrete for walls, shafts, slabs, decks and stairs
  • Paint
  • Base framing for connection to River
  • Install anchors for windows
  • Set and weld exterior walls
  • Set up lift system
  • Install glass
  • Set stairs
  • Install elevator machines and equipment
  • Install mechanical, electrical and plumbing equipment
  • Build out electrical, mechanical and pneumatic tube blower rooms
  • Install drywall
  • Load in and set air handling units
  • Install fire sprinkler systems
  • Install flooring
  • Demolition for connection points to Forest A
  • Interior activities: install mechanical, electrical, plumbing and drywall in River B patient family lounge; install infection prevention barriers and conduct demolition on lower level 1 of Forest A for building connections

Construction noise will be generated throughout the week. The demolition activities will be the loudest. Expect heavy truck traffic, primarily for concrete and steel delivery. Construction activity is weather-dependent and subject to change based on conditions.

All work will take place within standard construction hours: 8 a.m. to 6 p.m. Monday to Friday, and 9 a.m. to 6 p.m. on Saturday.

Please call 206-987-8000 or email construction@seattlechildrens.org with questions.


Stormwater Pipe Repair and Tree Removal, April 21 to April 23

From Tuesday, April 21 to Thursday, April 23, a construction crew will repair a broken stormwater pipe at the north end of the hospital campus, near NE 50th Street. This work will require the removal of some trees. Noise from excavators, chainsaws and wood chippers will be generated between 8 a.m. and 6 p.m. on those days. Please contact Meghan Fuller, manager of Grounds Maintenance, at 206-307-6687 if you have questions.


Street Parking Near the Hospital Campus

During the COVID-19 response, Seattle Children’s has been working hard to ensure our clinical staff can get to the hospital to care for patients. With cuts to public transit, a significant reduction in our shuttle service, and social distancing requirements — many more staff members are now driving alone. At the end of March, the City of Seattle implemented a temporary suspension of employee parking restrictions near the hospital campus and has authorized employee parking curbside on designated streets adjacent to the hospital, see map for locations. These measures will ensure essential health care workers can focus on delivering care to those that need it most, and not worry about where to park when traveling to the hospital for their shift.

We continue to encourage employees to use our onsite parking lots first before parking on the designated streets. Signs have been installed to mark where hospital employees are allowed to park. When parking permits are issued by our Transportation Department they will be managed in compliance with the City’s requirements.

Neighbors can call Seattle Children’s Security at 206-987-2030 for parking related issues or questions. For other questions, please call 206-987-8000 or email construction@seattlechildrens.org.